Installing sp2 on active/passive cluster
- From: "geekyguy" <geeky@xxxxxxx>
- Date: Mon, 31 Mar 2008 12:35:28 -0400
According to the sp2 readme:
3.2.5 Installing SQL Server 2005 SP2 on a Failover Cluster Instance
Note the following information before you install SP2 on a failover cluster instance:
Do not stop the cluster service before you run the SP2 Setup program, or while the installation program is running.
Do not end any running processes before you run the SP2 Setup program.
Do not take the SQL Server service off line before you run the SP2 Setup program. The SP2 Setup program will stop and start the SQL Server service.
Run the SP2 Setup program on the primary node of the failover cluster instance.
You must restart all failover cluster nodes after SP2 is finished installing.
Rolling upgrade is not supported for SP2.
I just want to make sure this is all I really have to do? I've read elsewhere that non-cluster-aware SQL components like Workstation Components/SMS will not be updated on the passive server unless I run sp2 on that server after running it on the active node?
I want to get this right the first time!
.
- Follow-Ups:
- Re: Installing sp2 on active/passive cluster
- From: Geoff N. Hiten
- Re: Installing sp2 on active/passive cluster
- Prev by Date: Re: Trying to Move Group - SQL Instance Won't Start
- Next by Date: 2 active instances on 2 nodes at the same time SQL 2k5 Standard
- Previous by thread: running sql 2005 sp2 on pre-sp1 cluster?
- Next by thread: Re: Installing sp2 on active/passive cluster
- Index(es):
Relevant Pages
|