Re: Drop-down list in Project
From: Guy S (anonymous_at_discussions.microsoft.com)
Date: 08/13/04
- Next message: Chris T.: "Reducing the file size"
- Previous message: Jan De Messemaeker: "Re: Drop-down list in Project"
- In reply to: Jan De Messemaeker: "Re: Drop-down list in Project"
- Messages sorted by: [ date ] [ thread ]
Date: Fri, 13 Aug 2004 07:36:59 -0700
Excellent! that worked a treat (for my boss!)
Many thanks
>-----Original Message-----
>Hi,
>
>You can have Value Lists on columns representing Custom
Fields (like Text7
>or Number11)
>They will necessarily be the same for the whole column
(no value list on an
>individual cell)
>Tools, Customize, Fields
>(Only for Project 2000 or +)
>HTH
>
>--
>Jan De Messemaeker
>Microsoft Project Most Valuable Professional
>http://users.online.be/prom-ade/index.htm
>32-495-300 620
>"Guy Shrimpton" <anonymous@discussions.microsoft.com>
wrote in message
>news:544701c48119$7010c810$a301280a@phx.gbl...
>> Can i input a drop-down list (like in Word) or data
>> validation list like in Excel, into a cell in project?
>>
>> Naturally, then i would duplicate this cell as many
times
>> as necessary, probably the whole column.
>>
>> Any ideas?
>>
>> Thanks in advance
>
>
>.
>
- Next message: Chris T.: "Reducing the file size"
- Previous message: Jan De Messemaeker: "Re: Drop-down list in Project"
- In reply to: Jan De Messemaeker: "Re: Drop-down list in Project"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|