Re: Problems entering data in resource usage table

From: Steve House (sjhouse.remove.this_at_to.send.hotmail.com)
Date: 08/04/04


Date: Wed, 4 Aug 2004 08:19:43 -0400

Resource usage displays the resource's scheduled work on tasks in hours per
time unit. The percentage allocated displays the resource's scheduled work
on tasks as a percentage of his full work schedule for the same period.
They're really two different ways of viewing the same piece of core
information. You're saying you want to change it in one view but NOT have
exactly the same information in another view change. Can't be done, how can
it be otherwise? Joe works 40 hours a week. I use the resource usage view
to assign him to work on something 1 hour on Monday and 4 hours on
Wednesday. He has now only got 35 hours in the week left to do other
things - I've used up 1/8 or 12% of his work week already and the allocation
percentage reflects that fact.

You really should thinking about how you're using Project - it is designed
to schedule the tasks arranged in a Project - it is a task scheduling tool,
NOT a personnel scheduling tool except incidentally to the schedule of the
tasks they're working on nor is it intended to schedule ongoing line of
business work as it sounds like you're trying to do. You said it yourself -
you're trying to schedule the *work in a whole department, NOT the work in
just 1 project* and yet the latter is what MSP is explicitly designed to do,
not the former. It's rather like buying a motorcycle and then getting
perplexed that it doesn't make good toast <grin>. You can certainly adapt
many tools to purposes for which they weren't designed but it usually is a
painful process with lots of bruised knuckles. In this case, the pain is
going to be to bite the bullet and do those inputs on a daily basis.

-- 
Steve House [MVP]
MS Project Trainer/Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
"Chris" <anonymous@discussions.microsoft.com> wrote in message
news:a71d01c47960$35150d90$a601280a@phx.gbl...
> I use the Resource usage table to input data - as I need
> to schedule repeat slots of work (1 day/week or month) for
> a whole department, not just 1 project.
> How do I stop it altering the Resource allocation - I want
> to be able to input against a week - and not have the
> resource jumping to 22% or whatever Project decides to do.
> I can get round this by inputting on a daily basis or by
> re-visiting those which go screwy on a daily basis - but
> it's a real pain.
> Any help appreciated!


Relevant Pages

  • Re: Full time resouce usage
    ... What you are describing here is optimisation and Project does not have that functionality inbuilt. ... If you want to optimise further you will have to manually adjust the hours allocated in either the Task Usage or Resource Usage views. ... By compressing all the tasks down in the way you are describing below produces a very risky schedule because it makes no allowance for you being off sick or being asked to do other high priority work for a while. ... Each set of task priorities and limits values get other scheduling (of cause I can manually to specify my scheduling but it not likely for me). ...
    (microsoft.public.project)
  • Re: Resource Availability Setting vs. Leveling
    ... give them a calendar that covers 50% of the ... > tasks that were set to resource usage of 100% were not scheduled while the ... > person was at 50% on the schedule. ...
    (microsoft.public.project)
  • Re: Graph colouring and local register allocation
    ... If we schedule to minimize register pressure, then allocate, then try ... to reschedule to maxmize ILP, ... allocation will require more registers, ... My point was that register allocation for ILP is not, ...
    (comp.compilers)
  • Re: Where to put tasks that cannot be scheduled yet?
    ... Run the resource leveling tool to resolve the overallocations. ... Project will schedule the tasks still to be worked for you, placing them on dates that gets the project done soonest. ... The only way I can find at present to overcome this is reduce the duration ... to "0" and put notes in the Task Allocation for the real duration - so that I ...
    (microsoft.public.project)
  • Re: scheduled work till the status date
    ... In the Resource Usage or Task Usage view you could add the Cumulative Work ... field to show how much work has been schedule as of a specific day. ...
    (microsoft.public.project)