Problems entering data in resource usage table

Tech-Archive recommends: Speed Up your PC by fixing your registry

From: Chris (anonymous_at_discussions.microsoft.com)
Date: 08/03/04

  • Next message: Joe: "Re: Changing units on all tasks"
    Date: Tue, 3 Aug 2004 06:45:58 -0700
    
    

    I use the Resource usage table to input data - as I need
    to schedule repeat slots of work (1 day/week or month) for
    a whole department, not just 1 project.
    How do I stop it altering the Resource allocation - I want
    to be able to input against a week - and not have the
    resource jumping to 22% or whatever Project decides to do.
    I can get round this by inputting on a daily basis or by
    re-visiting those which go screwy on a daily basis - but
    it's a real pain.
    Any help appreciated!


  • Next message: Joe: "Re: Changing units on all tasks"

    Relevant Pages

    • Re: Max units assignments for modeling purpuses
      ... Sometimes I see resources in resource sheet view that are in red, ... hourly or daily basis will still be red but if the overallocation ... You're welcome Gil. ...
      (microsoft.public.project)
    • VBA: getting information about the daily work assignment
      ... im trying to create a macro that will check what resources are assigned ... for what tasks on a daily basis. ... the Resource usage view)? ... galt's Profile: http://forums.techarena.in/members/101426.htm ...
      (microsoft.public.project)