Yes - but please be aware that entering Start or Finish dates is very bad
practice as this will create constraints which will reduce the flexibility
of your project. Enter Durations and the Precedence links and leave Project
to do what it is designed to do - calculate the Dates for you. :)

Mike Glen
Project MVP