Re: beginner: difficulties with timeline

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

From: Mike Glen (glenATmvps.org)
Date: 02/29/04


Date: Sun, 29 Feb 2004 09:29:23 -0000

Hi Fredo,

That's because the costed resource is assigned at zero hours work. Split
the screen and have a look at the assignments.

Mike Glen
MS Project MVP

Fredo Vincentis wrote:
> Thanks for the help on this, Mike. It gives me a good understanding
> on where I went wrong (or actually I didn't go too wrong, Project
> just handled things differently to what I expected).
>
> But if I may add another question that still causes me headache on
> the same project:
>
> Again there are some tasks that include multiple resources at the
> same time (e.g. a meeting between two people). One of the resources
> does not have a Std. Rate. assigned to it, because it is an external
> party that is not being paid for any of its work. The other resource
> has got a Std Rate of $65.00/h. The meeting goes for an hour (Mike:
> this would be for example Task 11).
>
> If I now change the View to "Cost" and check the "Total Cost" for one
> of these tasks, it says "$0.00". However, in my understanding Project
> should tell me the meeting cost $65.00, seeing that there is one
> resource with $65.00 and the other with $0.00 Std. Rate.
>
> This seems strange to me in particular because it is happening on
> some tasks of that kind and it doesn't on others. I have got several
> meetings of multiple resources throughout my project and some of them
> have got a Total Cost, others don't. I can't see the pattern.
>
> Any idea why this is happening?
>
> Thanks heaps for your help, guys! I am learning a lot here.
>
> "Mike Glen" <glenATmvps.org> wrote in message
> news:usJNjSf$DHA.3712@tk2msftngp13.phx.gbl...
>> For the record, Freda had, for example, 3 resources on a task, one
>> of whom had restricted working hours in a personal calendar. Thus
>> the Duration expanded to allow for all 3 resources to finish the
>> allotted Work. So the schedule, when levelled, pushed out the
>> dates, made the Duration longer.
>>
>> Mike Glen
>> MS Project MVP
>>
>> Mike Glen wrote:
>>> Sure, Fredo, email me changing the AT to @ and I'll have a look
>>> tomorrow.
>>>
>>> Mike Glen
>>> MS Project MVP
>>>
>>> Fredo Vincentis wrote:
>>>> I have got absolutely no time constraints on the project, except
>>>> for the beginning of the first task, which is set to a certain
>>>> date.
>>>>
>>>> Could I email the file to one of you to have a quick look over it?
>>>> Just to see that I enetered everything I needed before levelling?
>>>>
>>>> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
>>>> message news:e#vHGKu#DHA.2180@TK2MSFTNGP09.phx.gbl...
>>>>> Hi,
>>>>>
>>>>> I'm nearly sure that you assigned a task to a resource with
>>>>> limited availability in time
>>>>> Then when Leveling pushes a task for that resource to a time after
>>>>> its latest availability, it keeps on pushing till the end of its
>>>>> calendar (31/12/2049)
>>>>>
>>>>> Could you verify that?
>>>>>
>>>>> --
>>>>> Jan De Messemaeker
>>>>> Microsoft Project Most Valuable Professional
>>>>> Project Management Consultancy
>>>>> Prom+ade BVBA
>>>>> 32-495-300 620
>>>>> "Fredo Vincentis" <yahoda21@hotmailNoSpam.com> schreef in bericht
>>>>> news:c1e09p$1190$1@otis.netspace.net.au...
>>>>>> Hi guys, thanks for the welcome.
>>>>>>
>>>>>> I have read your article and others as well on levelling, but I
>>>>>> still don't get it working. What I really want project to do is
>>>>>> NOT to split any tasks (so I turned that setting off), and NOT to
>>>>>> adjust individual assignments. If there is overallocation, I want
>>>>>> the tasks to be pushed out longer until there is no more
>>>>>> overallocation.
>>>>>>
>>>>>> If I uncheck all tick boxes and leave the other default settings,
>>>>>> Project suddenly changes the duration of some of my tasks to
>>>>>> 0hrs!? That's one way of getting rid of the overallocation, but
>>>>>> not really implementable. I want the duration of the tasks to
>>>>>> remain the same.
>>>>>>
>>>>>> Also it changes the duration of my project from 26 days to 11962
>>>>>> days. I expected more like 40 days, not 32 years, to work on this
>>>>>> project.
>>>>>>
>>>>>> Any idea where I might be going wrong?
>>>>>>
>>>>>> Thanks heaps!
>>>>>>
>>>>>> "Mike Glen" <glenATmvps.org> wrote in message
>>>>>> news:evy5HLh#DHA.2660@TK2MSFTNGP10.phx.gbl...
>>>>>>> Hi ,
>>>>>>>
>>>>>>> Welcome to this Microsoft Project newsgroup :)
>>>>>>>
>>>>>>> You might like to have a look at my series of Microsoft Project
>>>>>>> lessons in the TechTrax ezine, particularly Lesson 5-Working
>>>>>>> With Resources, at this site:
>>>>>>>
>>>>>>
>>>>>
>>>>
>>>
>>
>
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AU
>>>>>> TH=23
>>>>>>>
>>>>>>> FAQs, companion products and other useful Project information
>>>>>>> can be seen at this web address: <http://www.mvps.org/project/>
>>>>>>>
>>>>>>> Hope this helps - please let us know how you get on :)
>>>>>>>
>>>>>>> Mike Glen
>>>>>>> MS Project MVP
>>>>>>>
>>>>>>>
>>>>>>> Fredo Vincentis wrote:
>>>>>>>> I have entered all my tasks into Project 2000, entered my
>>>>>>>> resources and allocated them to the tasks. I also set a few
>>>>>>>> predecessors for those tasks that rely on others to be
>>>>>>>> completed first. What I expected was that Project would start
>>>>>>>> a new task "as soon as possible" without overallocating
>>>>>>>> resources. But instead of doing that, all my resources are
>>>>>>>> hopelessly overallocated. I didn't change the start-times or
>>>>>>>> end-times, all I changed was the duration of each task.
>>>>>>>>
>>>>>>>> Any idea where I'm going wrong?
>>>>>>>>
>>>>>>>> Thanks for your help.



Relevant Pages

  • Re: How to force project not to split a task over multiple days
    ... > assignments. ... >> Hi Dave, ... >> MS Project MVP ... >>> day and multiple resources assigned. ...
    (microsoft.public.project)
  • Re: beginner: difficulties with timeline
    ... the screen and have a look at the assignments. ... > Again there are some tasks that include multiple resources at the ... > same time (e.g. a meeting between two people). ... >> MS Project MVP ...
    (microsoft.public.project)
  • Re: Assigning work resources to an hourly task
    ... one major flaw in Project is that you cannot lock resources to work together. ... If you resource level, ensure the meeting is given a priority of 1000 and you use Priority,Standard in the levelling dialog. ... Multiple resource assignments can be tricky to work out. ... John and Linda will attend the full one-hour meeting. ...
    (microsoft.public.project)
  • Re: Who Does What Reporing on Project Server
    ... are not using Project Server as it was intended, ... The only way to filter the Available resources list on the View resource ... The best way to limit the number of assignments shown in the View ... the Who Does What report by bringing your team members on board. ...
    (microsoft.public.project.pro_and_server)
  • Re: resource underallocation
    ... It sounds like she's asking leveling to create assignments - specifically to see the unused availablility of all the resources from day to day and have any unassigned percentage short of their maximum allocation to automatically be assigned to a MISC task. ...
    (microsoft.public.project)