Re: beginner: difficulties with timeline

From: Fredo Vincentis (yahoda21_at_hotmailNoSpam.com)
Date: 02/29/04


Date: Sun, 29 Feb 2004 11:07:02 +1100

Thanks for the help on this, Mike. It gives me a good understanding on where
I went wrong (or actually I didn't go too wrong, Project just handled things
differently to what I expected).

But if I may add another question that still causes me headache on the same
project:

Again there are some tasks that include multiple resources at the same time
(e.g. a meeting between two people). One of the resources does not have a
Std. Rate. assigned to it, because it is an external party that is not being
paid for any of its work. The other resource has got a Std Rate of $65.00/h.
The meeting goes for an hour (Mike: this would be for example Task 11).

If I now change the View to "Cost" and check the "Total Cost" for one of
these tasks, it says "$0.00". However, in my understanding Project should
tell me the meeting cost $65.00, seeing that there is one resource with
$65.00 and the other with $0.00 Std. Rate.

This seems strange to me in particular because it is happening on some tasks
of that kind and it doesn't on others. I have got several meetings of
multiple resources throughout my project and some of them have got a Total
Cost, others don't. I can't see the pattern.

Any idea why this is happening?

Thanks heaps for your help, guys! I am learning a lot here.

"Mike Glen" <glenATmvps.org> wrote in message
news:usJNjSf$DHA.3712@tk2msftngp13.phx.gbl...
> For the record, Freda had, for example, 3 resources on a task, one of whom
> had restricted working hours in a personal calendar. Thus the Duration
> expanded to allow for all 3 resources to finish the allotted Work. So the
> schedule, when levelled, pushed out the dates, made the Duration longer.
>
> Mike Glen
> MS Project MVP
>
> Mike Glen wrote:
> > Sure, Fredo, email me changing the AT to @ and I'll have a look
> > tomorrow.
> >
> > Mike Glen
> > MS Project MVP
> >
> > Fredo Vincentis wrote:
> >> I have got absolutely no time constraints on the project, except for
> >> the beginning of the first task, which is set to a certain date.
> >>
> >> Could I email the file to one of you to have a quick look over it?
> >> Just to see that I enetered everything I needed before levelling?
> >>
> >> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
> >> message news:e#vHGKu#DHA.2180@TK2MSFTNGP09.phx.gbl...
> >>> Hi,
> >>>
> >>> I'm nearly sure that you assigned a task to a resource with limited
> >>> availability in time
> >>> Then when Leveling pushes a task for that resource to a time after
> >>> its latest availability, it keeps on pushing till the end of its
> >>> calendar (31/12/2049)
> >>>
> >>> Could you verify that?
> >>>
> >>> --
> >>> Jan De Messemaeker
> >>> Microsoft Project Most Valuable Professional
> >>> Project Management Consultancy
> >>> Prom+ade BVBA
> >>> 32-495-300 620
> >>> "Fredo Vincentis" <yahoda21@hotmailNoSpam.com> schreef in bericht
> >>> news:c1e09p$1190$1@otis.netspace.net.au...
> >>>> Hi guys, thanks for the welcome.
> >>>>
> >>>> I have read your article and others as well on levelling, but I
> >>>> still don't get it working. What I really want project to do is NOT
> >>>> to split any tasks (so I turned that setting off), and NOT to
> >>>> adjust individual assignments. If there is overallocation, I want
> >>>> the tasks to be pushed out longer until there is no more
> >>>> overallocation.
> >>>>
> >>>> If I uncheck all tick boxes and leave the other default settings,
> >>>> Project suddenly changes the duration of some of my tasks to 0hrs!?
> >>>> That's one way of getting rid of the overallocation, but not really
> >>>> implementable. I want the duration of the tasks to remain the same.
> >>>>
> >>>> Also it changes the duration of my project from 26 days to 11962
> >>>> days. I expected more like 40 days, not 32 years, to work on this
> >>>> project.
> >>>>
> >>>> Any idea where I might be going wrong?
> >>>>
> >>>> Thanks heaps!
> >>>>
> >>>> "Mike Glen" <glenATmvps.org> wrote in message
> >>>> news:evy5HLh#DHA.2660@TK2MSFTNGP10.phx.gbl...
> >>>>> Hi ,
> >>>>>
> >>>>> Welcome to this Microsoft Project newsgroup :)
> >>>>>
> >>>>> You might like to have a look at my series of Microsoft Project
> >>>>> lessons in the TechTrax ezine, particularly Lesson 5-Working With
> >>>>> Resources, at this site:
> >>>>>
> >>>>
> >>>
> >>
> >
>
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AU
> >>>> TH=23
> >>>>>
> >>>>> FAQs, companion products and other useful Project information can
> >>>>> be seen at this web address: <http://www.mvps.org/project/>
> >>>>>
> >>>>> Hope this helps - please let us know how you get on :)
> >>>>>
> >>>>> Mike Glen
> >>>>> MS Project MVP
> >>>>>
> >>>>>
> >>>>> Fredo Vincentis wrote:
> >>>>>> I have entered all my tasks into Project 2000, entered my
> >>>>>> resources and allocated them to the tasks. I also set a few
> >>>>>> predecessors for those tasks that rely on others to be completed
> >>>>>> first. What I expected was that Project would start a new task
> >>>>>> "as soon as possible" without overallocating resources. But
> >>>>>> instead of doing that, all my resources are hopelessly
> >>>>>> overallocated. I didn't change the start-times or end-times, all
> >>>>>> I changed was the duration of each task.
> >>>>>>
> >>>>>> Any idea where I'm going wrong?
> >>>>>>
> >>>>>> Thanks for your help.
>
>
>



Relevant Pages

  • Re: beginner: difficulties with timeline
    ... Again there are some tasks that include multiple resources at the same time ... The meeting goes for an hour (Mike: this would be for example Task 11). ... in my understanding Project should ...
    (microsoft.public.project)
  • Re: Will the quitstart toolbar takes up the resources too?
    ... > Thank you, Mike. ... > Will the quitstart toolbar takes up the resources too? ... > Unless you install programs to the desktop, program icons are just ... > and has to have resources allocated to ALWAYS keep it there.. ...
    (microsoft.public.windowsxp.general)
  • Re: Swapping Resources ?
    ... Sure that makes sense but if Mike is replaced by Jim and both Mike and Jim ... Resources dialog box. ... After replacing Jim with Mike, shouldn't Jim's name no longer be ...
    (microsoft.public.project)
  • Re: General Task Question Please Help
    ... Mike. ... MS Project MVP ... task which you will allow 2 resources 1 week to complete. ... I have searched through the help and this basic information is not ...
    (microsoft.public.project)
  • Re: How to force project not to split a task over multiple days
    ... Thanks Mike. ... You're simpler suggestion of taking the workshop off the plan will not work ... on all the other constraints and assignments. ... >> day and multiple resources assigned. ...
    (microsoft.public.project)