Re: beginner: difficulties with timeline
From: Mike Glen (glenATmvps.org)
Date: 02/28/04
- Previous message: JackD: "Re: Licences???"
- In reply to: Mike Glen: "Re: beginner: difficulties with timeline"
- Next in thread: Fredo Vincentis: "Re: beginner: difficulties with timeline"
- Reply: Fredo Vincentis: "Re: beginner: difficulties with timeline"
- Messages sorted by: [ date ] [ thread ]
Date: Sat, 28 Feb 2004 12:14:55 -0000
For the record, Freda had, for example, 3 resources on a task, one of whom
had restricted working hours in a personal calendar. Thus the Duration
expanded to allow for all 3 resources to finish the allotted Work. So the
schedule, when levelled, pushed out the dates, made the Duration longer.
Mike Glen
MS Project MVP
Mike Glen wrote:
> Sure, Fredo, email me changing the AT to @ and I'll have a look
> tomorrow.
>
> Mike Glen
> MS Project MVP
>
> Fredo Vincentis wrote:
>> I have got absolutely no time constraints on the project, except for
>> the beginning of the first task, which is set to a certain date.
>>
>> Could I email the file to one of you to have a quick look over it?
>> Just to see that I enetered everything I needed before levelling?
>>
>> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
>> message news:e#vHGKu#DHA.2180@TK2MSFTNGP09.phx.gbl...
>>> Hi,
>>>
>>> I'm nearly sure that you assigned a task to a resource with limited
>>> availability in time
>>> Then when Leveling pushes a task for that resource to a time after
>>> its latest availability, it keeps on pushing till the end of its
>>> calendar (31/12/2049)
>>>
>>> Could you verify that?
>>>
>>> --
>>> Jan De Messemaeker
>>> Microsoft Project Most Valuable Professional
>>> Project Management Consultancy
>>> Prom+ade BVBA
>>> 32-495-300 620
>>> "Fredo Vincentis" <yahoda21@hotmailNoSpam.com> schreef in bericht
>>> news:c1e09p$1190$1@otis.netspace.net.au...
>>>> Hi guys, thanks for the welcome.
>>>>
>>>> I have read your article and others as well on levelling, but I
>>>> still don't get it working. What I really want project to do is NOT
>>>> to split any tasks (so I turned that setting off), and NOT to
>>>> adjust individual assignments. If there is overallocation, I want
>>>> the tasks to be pushed out longer until there is no more
>>>> overallocation.
>>>>
>>>> If I uncheck all tick boxes and leave the other default settings,
>>>> Project suddenly changes the duration of some of my tasks to 0hrs!?
>>>> That's one way of getting rid of the overallocation, but not really
>>>> implementable. I want the duration of the tasks to remain the same.
>>>>
>>>> Also it changes the duration of my project from 26 days to 11962
>>>> days. I expected more like 40 days, not 32 years, to work on this
>>>> project.
>>>>
>>>> Any idea where I might be going wrong?
>>>>
>>>> Thanks heaps!
>>>>
>>>> "Mike Glen" <glenATmvps.org> wrote in message
>>>> news:evy5HLh#DHA.2660@TK2MSFTNGP10.phx.gbl...
>>>>> Hi ,
>>>>>
>>>>> Welcome to this Microsoft Project newsgroup :)
>>>>>
>>>>> You might like to have a look at my series of Microsoft Project
>>>>> lessons in the TechTrax ezine, particularly Lesson 5-Working With
>>>>> Resources, at this site:
>>>>>
>>>>
>>>
>>
>
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AU
>>>> TH=23
>>>>>
>>>>> FAQs, companion products and other useful Project information can
>>>>> be seen at this web address: <http://www.mvps.org/project/>
>>>>>
>>>>> Hope this helps - please let us know how you get on :)
>>>>>
>>>>> Mike Glen
>>>>> MS Project MVP
>>>>>
>>>>>
>>>>> Fredo Vincentis wrote:
>>>>>> I have entered all my tasks into Project 2000, entered my
>>>>>> resources and allocated them to the tasks. I also set a few
>>>>>> predecessors for those tasks that rely on others to be completed
>>>>>> first. What I expected was that Project would start a new task
>>>>>> "as soon as possible" without overallocating resources. But
>>>>>> instead of doing that, all my resources are hopelessly
>>>>>> overallocated. I didn't change the start-times or end-times, all
>>>>>> I changed was the duration of each task.
>>>>>>
>>>>>> Any idea where I'm going wrong?
>>>>>>
>>>>>> Thanks for your help.
- Previous message: JackD: "Re: Licences???"
- In reply to: Mike Glen: "Re: beginner: difficulties with timeline"
- Next in thread: Fredo Vincentis: "Re: beginner: difficulties with timeline"
- Reply: Fredo Vincentis: "Re: beginner: difficulties with timeline"
- Messages sorted by: [ date ] [ thread ]
Relevant Pages
|