Re: beginner: difficulties with timeline

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance

From: Mike Glen (glenATmvps.org)
Date: 02/28/04

  • Next message: Fredo Vincentis: "Re: beginner: difficulties with timeline"
    Date: Sat, 28 Feb 2004 12:14:55 -0000
    
    

    For the record, Freda had, for example, 3 resources on a task, one of whom
    had restricted working hours in a personal calendar. Thus the Duration
    expanded to allow for all 3 resources to finish the allotted Work. So the
    schedule, when levelled, pushed out the dates, made the Duration longer.

    Mike Glen
    MS Project MVP

    Mike Glen wrote:
    > Sure, Fredo, email me changing the AT to @ and I'll have a look
    > tomorrow.
    >
    > Mike Glen
    > MS Project MVP
    >
    > Fredo Vincentis wrote:
    >> I have got absolutely no time constraints on the project, except for
    >> the beginning of the first task, which is set to a certain date.
    >>
    >> Could I email the file to one of you to have a quick look over it?
    >> Just to see that I enetered everything I needed before levelling?
    >>
    >> "Jan De Messemaeker" <jandemes at prom hyphen ade dot be> wrote in
    >> message news:e#vHGKu#DHA.2180@TK2MSFTNGP09.phx.gbl...
    >>> Hi,
    >>>
    >>> I'm nearly sure that you assigned a task to a resource with limited
    >>> availability in time
    >>> Then when Leveling pushes a task for that resource to a time after
    >>> its latest availability, it keeps on pushing till the end of its
    >>> calendar (31/12/2049)
    >>>
    >>> Could you verify that?
    >>>
    >>> --
    >>> Jan De Messemaeker
    >>> Microsoft Project Most Valuable Professional
    >>> Project Management Consultancy
    >>> Prom+ade BVBA
    >>> 32-495-300 620
    >>> "Fredo Vincentis" <yahoda21@hotmailNoSpam.com> schreef in bericht
    >>> news:c1e09p$1190$1@otis.netspace.net.au...
    >>>> Hi guys, thanks for the welcome.
    >>>>
    >>>> I have read your article and others as well on levelling, but I
    >>>> still don't get it working. What I really want project to do is NOT
    >>>> to split any tasks (so I turned that setting off), and NOT to
    >>>> adjust individual assignments. If there is overallocation, I want
    >>>> the tasks to be pushed out longer until there is no more
    >>>> overallocation.
    >>>>
    >>>> If I uncheck all tick boxes and leave the other default settings,
    >>>> Project suddenly changes the duration of some of my tasks to 0hrs!?
    >>>> That's one way of getting rid of the overallocation, but not really
    >>>> implementable. I want the duration of the tasks to remain the same.
    >>>>
    >>>> Also it changes the duration of my project from 26 days to 11962
    >>>> days. I expected more like 40 days, not 32 years, to work on this
    >>>> project.
    >>>>
    >>>> Any idea where I might be going wrong?
    >>>>
    >>>> Thanks heaps!
    >>>>
    >>>> "Mike Glen" <glenATmvps.org> wrote in message
    >>>> news:evy5HLh#DHA.2660@TK2MSFTNGP10.phx.gbl...
    >>>>> Hi ,
    >>>>>
    >>>>> Welcome to this Microsoft Project newsgroup :)
    >>>>>
    >>>>> You might like to have a look at my series of Microsoft Project
    >>>>> lessons in the TechTrax ezine, particularly Lesson 5-Working With
    >>>>> Resources, at this site:
    >>>>>
    >>>>
    >>>
    >>
    >
    http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AU
    >>>> TH=23
    >>>>>
    >>>>> FAQs, companion products and other useful Project information can
    >>>>> be seen at this web address: <http://www.mvps.org/project/>
    >>>>>
    >>>>> Hope this helps - please let us know how you get on :)
    >>>>>
    >>>>> Mike Glen
    >>>>> MS Project MVP
    >>>>>
    >>>>>
    >>>>> Fredo Vincentis wrote:
    >>>>>> I have entered all my tasks into Project 2000, entered my
    >>>>>> resources and allocated them to the tasks. I also set a few
    >>>>>> predecessors for those tasks that rely on others to be completed
    >>>>>> first. What I expected was that Project would start a new task
    >>>>>> "as soon as possible" without overallocating resources. But
    >>>>>> instead of doing that, all my resources are hopelessly
    >>>>>> overallocated. I didn't change the start-times or end-times, all
    >>>>>> I changed was the duration of each task.
    >>>>>>
    >>>>>> Any idea where I'm going wrong?
    >>>>>>
    >>>>>> Thanks for your help.


  • Next message: Fredo Vincentis: "Re: beginner: difficulties with timeline"

    Relevant Pages

    • Re: beginner: difficulties with timeline
      ... For the record, Freda had, for example, 3 resources on a task, one of whom ... schedule, when levelled, pushed out the dates, made the Duration longer. ... > MS Project MVP ... > Fredo Vincentis wrote: ...
      (microsoft.public.project)
    • Re: Ways to analyze project to cut time
      ... You're welcome, Craig, and good luck! ... MS Project MVP ... Adding resources in a resource driven task to save time. ... In actuality duration doesn't get anything done, ...
      (microsoft.public.project)
    • Re: Task duration based on calculation
      ... You're welcome, Chris :-) ... MS Project MVP ... duration before I assign resources to it. ...
      (microsoft.public.project)
    • Re: What should be put into a duration?
      ... the availability of the resources required to do the work. ... usually assign a resource at 100% - if Bob is assigned to wax widgets I'm ... So when I input the task I'm going to estimate its duration and let Project ... the training should be split out as individual tasks in their own ...
      (microsoft.public.project)
    • Re: Isnt there a "Machine" Resource Type???
      ... I may also have to go back and fix the duration ... The answer is there is only ONE CLASS used for allocated resources, ... Fixed units, fixed work, and fixed duration only applies to what happens ... SCHEDULE these d_mn tasks. ...
      (microsoft.public.project)