Re: Physical Percent (%) Complete (task field)
- From: "Dale Howard [MVP]" <dale[dot]howard[at]msprojectexperts[dot]com>
- Date: Sat, 1 May 2010 15:43:20 -0400
ks2008 --
Yes, you are correct. The PM must manually enter the Physical % Complete value on a task by task basis. Beyond this, the Physical % Complete value DOES NOT roll up to summary tasks and to the Project Summary Task, nor can you enter progress on summary tasks and the Project Summary Task. Hope this helps.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"ks2008" <ks2008@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:725AA0A1-7D94-4D99-8EF6-FB6A8666CB5B@xxxxxxxxxxxxxxxx
Dear All,.
"Physical Percent (%) Complete (task field)"
Looks like data in this field manually populated , Am I correct ?
Thanks
KS
- Follow-Ups:
- References:
- Physical Percent (%) Complete (task field)
- From: ks2008
- Physical Percent (%) Complete (task field)
- Prev by Date: Re: ID field not showing
- Next by Date: Re: Physical Percent (%) Complete (task field)
- Previous by thread: Physical Percent (%) Complete (task field)
- Next by thread: Re: Physical Percent (%) Complete (task field)
- Index(es):
Relevant Pages
|