hammock vs summary task
- From: KingKikapu <KingKikapu.41wrvc@xxxxxxxxxxxxx>
- Date: Thu, 19 Nov 2009 22:39:13 +0530
Hello folks
I have a bit of an issue: I am currently using a large number of
hammock tasks (the linked field kind) in my project files (designed to
capture any costs that cannot be easily broken down by the related
sub-tasks). As an example, I have a Framing hammock that captures any
material costs that cannot easily be placed on the individual floor
framing tasks. Now, I am also running an Earned Value system that is
duration based, so these hammock tasks definitely have an associated
planned value at any given moment. The problem is that I now have
something of around 15-20 hammock tasks on every building project file,
and when these files are accessed remotely, I find it takes 10-20
minutes to load the bloody file (I am using MSP 2007 Pro, and that is
not changing anytime soon).
I need to do something about this. I have two choices available to me:
I can either run a terminal system back to the home server (thereby
technically running the file from the source and removing the 10-15
minute lag) or I can apply the resources that were intended for the
hammock onto the summary task that best matches.
I know that's considered bad form, but I don't quite understand why.
Could someone explain to me how that would mess things (mostly EVM) up?
Suggestions?
Thanks as always.
--
KingKikapu
------------------------------------------------------------------------
KingKikapu's Profile: http://forums.techarena.in/members/119086.htm
View this thread: http://forums.techarena.in/microsoft-project/1273087.htm
http://forums.techarena.in
.
- Follow-Ups:
- Re: hammock vs summary task
- From: Steve House
- RE: hammock vs summary task
- From: Jim Aksel
- Re: hammock vs summary task
- Prev by Date: RE: Business conference planning template
- Next by Date: Error message when adding text to bar
- Previous by thread: Business conference planning template
- Next by thread: RE: hammock vs summary task
- Index(es):