Re: Activty % complete moves after status date
- From: Terri <Terri@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Fri, 9 Oct 2009 09:02:02 -0700
Thank you very much
"JulieS" wrote:
Hello Terri,.
Are you referring to the Progress Bar showing in the Gantt chart
which by default draws from the Actual Start to CompleteThrough? I
usually prefer drawing the progress bar from Actual Start through
Stop, which is the end of recorded progress.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Terri" <Terri@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:A0417952-FBD4-4998-9E00-45D0FB88BA48@xxxxxxxxxxxxxxxx
Can anyone explain WHY Project moves the activity percent complete
past the
status date?? My staus is Complete Through Friday 5:00PM, when I
set the
status on an activity to Friday at 5:00PM, Project automatically
moves the
percent complete through SUNDAY 5:00PM, or if Monday is a holiday,
progress
move to Monday 5:00PM
Please don't tell me it is because Sat. & Sun. are not working
days. Status
date is Friday, progress SHOULD NOT move past that set date.
The only time this works correctly in Project is on an activity
with a 7 day
calendar.
I need a decent explanation for my PM (other than that's just what
Project
does) why progress is showing through Sunday when the status date
is Friday.
- References:
- Activty % complete moves after status date
- From: Terri
- Re: Activty % complete moves after status date
- From: JulieS
- Activty % complete moves after status date
- Prev by Date: Re: Getting Started: I have an idea of how I want to setup my proj
- Next by Date: Re: Activty % complete moves after status date
- Previous by thread: Re: Activty % complete moves after status date
- Next by thread: Re: Activty % complete moves after status date
- Index(es):
Relevant Pages
|