Re: Activty % complete moves after status date

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Hello Terri,

Are you referring to the Progress Bar showing in the Gantt chart
which by default draws from the Actual Start to CompleteThrough? I
usually prefer drawing the progress bar from Actual Start through
Stop, which is the end of recorded progress.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Terri" <Terri@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:A0417952-FBD4-4998-9E00-45D0FB88BA48@xxxxxxxxxxxxxxxx
Can anyone explain WHY Project moves the activity percent complete
past the
status date?? My staus is Complete Through Friday 5:00PM, when I
set the
status on an activity to Friday at 5:00PM, Project automatically
moves the
percent complete through SUNDAY 5:00PM, or if Monday is a holiday,
progress
move to Monday 5:00PM

Please don't tell me it is because Sat. & Sun. are not working
days. Status
date is Friday, progress SHOULD NOT move past that set date.

The only time this works correctly in Project is on an activity
with a 7 day
calendar.

I need a decent explanation for my PM (other than that's just what
Project
does) why progress is showing through Sunday when the status date
is Friday.


.



Relevant Pages

  • Re: Custom CRect Question
    ... Our progress bar needs to keep track of the current frame, total frames in ... the session, the session number, and total number of sessions. ... So what this sounds like is you have several "bars", one of which is a progress along the ... So this isn't a stacked progress bar, ...
    (microsoft.public.vc.mfc)
  • RE: ProgressBar display
    ... is loading the tab controls, so while the thread is loading the tab page the ... progress bar will not be shown until the thread gets chance to execute its ... private void timer1_Tick ...
    (microsoft.public.dotnet.languages.csharp)
  • Re: Simple thread implementation not working.
    ... Dim t As Thread ... I dont care how long the progress bar is run so I abort it once the add ... with the add printer it does not start until the printer function is ...
    (microsoft.public.dotnet.languages.vb)
  • Re: Additional progress startup bar
    ... Sometimes, if there is a firmware update, you'll see a progress ... Firmware updates without your permission or knowledge on the ... Perhaps because he wasn't aware that a progress bar would be part ...
    (comp.sys.mac.advocacy)
  • Re: Progress indicators (reprise)
    ... I tried reimplementing the traditional "progress bar" ... with an emphasis on more accurately reporting *actual* ... first metric (e.g., average size of each entry is XXX, min is ...
    (comp.arch.embedded)