- From: Rob Schneider <rmschne@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Tue, 06 Oct 2009 13:45:33 +0100
Can't get my head completely about what you want to do, but I'm pretty sure that this sort of specialty report not included in the standard set of reports.
I guess what I would do to tackle this sort of report would be to sponsor the development of a program in VBA that pulled out the successor tasks as you defined. The program would construct (probably) report in HTML (since it's relatively simple and generic for viewing by a browser). If the data and relationships are in the plan, and if the report can be specified, then pretty much anything possible via VBA.
--rms
www.rmschneider.com
mikejw wrote:
Hello,.
I am working in MS Project 2007 in one file and would like to show on a report successors that are linked to another subsystem/wbs. I would also like to show the dates on the current task and its successor. The objective is to show the subsystem manager just their successor links outside of there domain so that they can see how a slipped date might impact another subsystem. I know I can show this on a network diagram but would like to give them a report.
Thanks, Mike
- References:
- show only successors to tasks outside wbs
- From: mikejw
- show only successors to tasks outside wbs
- Prev by Date: Easy question: How to assign part-time supervisors?
- Next by Date: Re: Difference between MSProject 2003 and 2007 handling vacation t
- Previous by thread: show only successors to tasks outside wbs
- Next by thread: Re: show only successors to tasks outside wbs
- Index(es):
Relevant Pages
|
Loading