Re: Task Start Date & Assignment Delay
- From: "Mike Glen" <glen@xxxxxxxx>
- Date: Thu, 3 Sep 2009 22:51:53 +0100
You're welcome, Angela :-)
You mention the word "enterprise", what version of Project are you using?
You said: "No constraints were introduced in the project after my changes". OK, but I asked if there were any constraints. Check View/Table ()/More Tables.../Constraint Dates, and make sure they are all "As Soon As Possible".
Check the project and resource calendars to see if there is any restrictions on resources over your period of concern.
Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
"ABG" <ABG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:4EC71F5C-AC30-4AF7-8177-65BB24F39B7B@xxxxxxxxxxxxxxxx
Hi Mke,
Thanks again for your replies!
To answer your questions:
- No constrains were introduced in the project after my changes
- Is the Project Start Date correct? yes
- Have I assigned resources? yes. I took over that project and it already
had the resources added and assigned to tasks and I have been adding new
resources
- Are all resources available at the beginning of the project? yes
- Are there any resource or task calendars? We have a project enterprise
environment & that includes resources. We are running on 2007 (all projects
got migrated from 2003 to 2007 about a month ago)
Unfortunately I won't be able to email you the project; the Company policies
don't allow us to do that. However, I am keeping a closer eye on this
project and so far, it has been fine now.
Thanks Mike, I appreciate it!
"Mike Glen" wrote:
Sorry - slip of the visuals, for Mike read Angela!!!!!!!!!
Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
"Mike Glen" <glen@xxxxxxxx> wrote in message
news:eTJKZflKKHA.1252@xxxxxxxxxxxxxxxxxxxxxxx
> You're welcome, Mike :-)
>
> I'm a bit concerned that your changing of the start dates will have
> introduced Start No Earlier Than constraints. [Enter task names,
> Durations and Precedence links and let Project do what it is designed > to
> do - create the schedule for you ] Is the Project Start Date correct?
> Have you assigned resources? Are all resources available at the > beginning
> of your project? Are there any resource or task calendars? As you can
> see, there are many factors involved. If you care to zip up your > project
> and email it to me, I'll have a look to see if I can find what's amiss.
>
> Mike Glen
> MS Project MVP
> See http://tinyurl.com/2xbhc for my free Project Tutorials
>
>
> "ABG" <ABG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
> news:9AF7EF56-CCF9-4449-848D-5F9AEC141BCF@xxxxxxxxxxxxxxxx
>> Thanks Mike!
>>
>> I verified the Constraint dates and didn't see any constraints; all >> tasks
>> were setup with the 'As soon as possible' constraint. I ended up >> having
>> to
>> change the start date in the task usage view for each of the >> resources; I
>> still don't know how the 'assignment delay' field got changed though. >> :(
>>
>> Thanks Mike!
>>
>> "Mike Glen" wrote:
>>
>>> Hi Angela,
>>>
>>> Welcome to this Microsoft Project newsgroup :)
>>>
>>> It sounds like a Finish No Later Than constraint. View/Tables().More
>>> Tables... and select the Constraint Dates table. Make all >>> constraints
>>> As
>>> Soon As Possible.
>>>
>>> FAQs, companion products and other useful Project information can be
>>> seen at
>>> this web address: http://project.mvps.org/faqs.htm
>>>
>>> Hope this helps - please let us know how you get on :)
>>>
>>> Mike Glen
>>> MS Project MVP
>>> See http://tinyurl.com/2xbhc for my free Project Tutorials
>>>
>>>
>>>
>>> "ABG" <ABG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
>>> news:6EA19977-D648-4509-9421-EA3AF4BD1731@xxxxxxxxxxxxxxxx
>>> >I have a task that should start on 8/31, but project is scheduling >>> >all
>>> >the
>>> > resources to start working on that task on 10/2 (Fixed Work, >>> > resources
>>> > 100%
>>> > units, 2hrs work). I have verified all the resources and I don't >>> > see
>>> > an
>>> > obvious reason why this task is being delayed (the 'assignment >>> > delay'
>>> > field
>>> > under the Task Usage view shows a '39.39 days' delay). I have not
>>> > done
>>> > any
>>> > leveling on the project, nor recall making changes to this field.
>>> >
>>> > Can someone explain how this could have happened and also if its >>> > safe
>>> > to
>>> > try
>>> > to change the assignment delay days so that my project gets back on
>>> > track?
>>> >
>>> > Thanks in advance!
>>> > Angela
>>>
>>>
>
.
- References:
- Re: Task Start Date & Assignment Delay
- From: ABG
- Re: Task Start Date & Assignment Delay
- Prev by Date: Re: Task Start Date & Assignment Delay
- Next by Date: Re: Delete blank pages at the bottom
- Previous by thread: Re: Task Start Date & Assignment Delay
- Index(es):
Relevant Pages
|
Loading