Re: Rolling Contractor Updates up to Master Schedule on Const. Project
- From: Rob Schneider <rmschne@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 03 Sep 2009 06:35:54 +0100
Gosh. My brain hurts. Why no go straight to the beer and discuss there!
--rms
www.rmschneider.com
Andrew Lavinsky wrote:
Saw Rod Gill's posting on MS Project vs. Primavera which prompted me to post this and see if I can pick the group's collective brains......
I am working with a company that manages construction. They have schedules arranged in tiers, with the overall schedule being tracked at a tier 1-3 level, and the contractors tracking their own schedules at tier 4+. The contractors may track their schedule using any scheduling software, not necessarily MPP. We are not using "master" schedules as typically identified in MPP parlance, but rather a "master" schedule as an overall schedule of the entire project (i.e. no linked subprojects, etc.)
The goal is to roll up the credit (% Complete and/or Physical % Complete, but most likely the latter) from the tier 4+ schedules to the tier 3 master schedule. This process will be performed by dedicated schedulers. Effort and cost is not relevant to this exercise at this point.
As Rod described it in his post on 8/19: "For example we have trackers in Excel to report progress in the shop for Pipe fabrication and trackers for teams on site to report pipe installation progress. Using Pipe numbers Project can update progress at a pipe level (through VBA) even though the tracker works at drawing level (up to 20 drawings per pipe) and Project is mostly at Pipe level." That's pretty similar to some of our examples, although we have a number of different types of tasks to track, not just Pipe construction.
Just curious how other folks have met this challenge, and if there are any recommendations I can garner from their experiences.
Thanks in advance. Responders who also attend the Project Conference may get rewarded with a free beer.
- References:
- Rolling Contractor Updates up to Master Schedule on Const. Project
- From: Andrew Lavinsky
- Rolling Contractor Updates up to Master Schedule on Const. Project
- Prev by Date: RE: Tasks' durations vs Project Duration
- Next by Date: Re: MS Project vs. Primavera
- Previous by thread: Rolling Contractor Updates up to Master Schedule on Const. Project
- Next by thread: Re: Rolling Contractor Updates up to Master Schedule on Const. Project
- Index(es):
Relevant Pages
|