Re: Key tips while changing schedules

Tech-Archive recommends: Fix windows errors by optimizing your registry



Thanks Julie..So you mean to say it is better practice to change the duration
for tracking. One more query i have is

1. If we change the % complete, will the Start date and duration change
automatically?

--

Thanks and Regards,
Aravind G


"JulieS" wrote:

Hello Aravind G,

I assume you are referring to tracking when you ask about "updating"
schedules. So, a couple of quick tips:

1) Save a baseline before providing any tracking data to tasks. You
may not wish to baseline the entire project file at once depending
upon your project, but you should baseline tasks before tracking.

2) If you feel your project may be very volatile, consider saving a
copy of the baseline into one of the spare baseline fields --
Baseline 10 for example. Then if you should need to rebaseline due
to a significant change (loss of resources for example) you can
rebaseline and still have a copy of the original baseline stored.

3) If tracking at a task level, update Actual Duration and Remaining
Duration to have Project calculate % complete or update Work and
Remaining work to have Project calculate % work complete.

4) If you have the data available, consider tracking Actual and
Remaining work in either the Task Usage or Resource Usage views.
This allows you to still track variances if the task was completed
as was originally scheduled but the amount of actual work was
different than initially planned.

I imagine others will check in with their thoughts as well.


I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project



"Aravind G" <AravindG@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:3E60EDFE-D661-4B82-BD8B-F3C1A155D634@xxxxxxxxxxxxxxxx
Hi,

I'm currently in the process of knowing more about Project 2007.
Can anyone
give me a list of key tips or pointers that one should be keeping
in mind
while updating schedules?

--

Thanks and Regards,
Aravind G



.



Relevant Pages

  • Re: Key tips while changing schedules
    ... Actual and Remaining Duration -- Project will calculate those values for you. ... I personally display the Tracking table and fill in: ... Save a baseline before providing any tracking data to tasks. ... while updating schedules? ...
    (microsoft.public.project)
  • Re: Tracking Actuals / Adjusting units?
    ... Show the Tracking Gantt View ... deal with Actual Start Date, Actual Duration, Remaining Duration (0 if the ... Get the hang of the buttons on the Tracking Toolbar. ... I've a question about how to adjust actuals after setting a baseline. ...
    (microsoft.public.project)
  • Re: Planned vs. Actual
    ... There is Start, Finish, Duration, and Work and then there is Actual Start, Actual Finish, Actual Duration, and Actual Work. ... There is also a third set of fields, the Baseline Start, Baseline Finish, Baseline Duration, and Baseline Work fields. ... When you enter values on the Entry table as you have done, you are not updating it with Actuals, you are changing the scheduled. ... On the other hand, if you display the Tracking Table and enter a date into the Actual Start field, it is connected to the Start with a one-way link and the Start gets updated to match whatever you entered in the Actual Meanwhile, the values in the Baseline fields are NOT connected with an automatic update to either the Start or Actual Start so they still hold your original plan in order to allow you to compare it to the way things are working out. ...
    (microsoft.public.project)
  • Re: BCWP and BCWS
    ... If I go with tracking actual against remaining durations, ... No you shouldn't save a new baseline. ... If you use fixed costs as Andrew ... all that is provided to me is a lump sum cost from the contractor ...
    (microsoft.public.project)
  • RE: Best way to import data.
    ... No need for macros. ... due to what is actually occuring -- that's called tracking. ... Save a baseline for your project to copy the Start, Finish, Duration, Work, ...
    (microsoft.public.project)