Re: using MS Project for tasks tracking- not hours/effort or work tracking

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Lisa@IMC wrote:
Rob,

Thanks for your reply; I appreciate you taking the time to help me
out.

Prior to my managing the projects there wasn't anyone that tracked it. This is a new venture for the company (we were recently purchased and
thus my role was created). I am responsible for defining the plan and
completion dates so I am the Project Manager. I have taken 2 MS project
classes and understand the concepts.

We sell an off the shelf product that does not require software
development, we do not charge for my or anyone else's time and are not
worried about costs or budgets. My role is to ensure that stuff gets
done when I determine it should.

The CEO has told me that he wants me to start using project to schedule
and track the implementations, and some of our RFP's require that we
provide a plan in project.

The role that new management has in mind is that I ensure that the
following things occur:

- communication with the Client regarding the process & require
responsibilities on their part
- installation of the purchased software
- scheduling and completion of training
- configuration of software interfaces
- scheduling of software "Go Live" with the client
- tracking of data conversion projects. The start and end dates for
these are determined by me and the programmer.
- determination of risk and communication to stakeholders
Some of these items have to occur in a specific order and within
certain number of days prior to "go live"

When I referenced rescheduling a task I was referring to an issue that
has just occurred:
A task was slated to finish on 7/7/09. My tech just informed
me that the client does not have the required hardware to complete the
task and is unsure when they will have said hardware. I am wondering do
I leave it as a slipping task or reschedule it for completion once the
HW is in place.

So I guess in summary: I am required to use Ms Project, ( which I like
using). I am looking for feedback as to best practices for my
situation.



Cool. Now we have something to work with. Will cogitate and get back to you soon.
.



Relevant Pages

  • Re: Outlook and OWA calendars not staying in sync
    ... take client calls and based on these calls make appointments for upto ... Those taking these appointments are using Outlook 2003; ... viewed by the scheduling staff, and yet, even at the same time the ...
    (microsoft.public.exchange.admin)
  • Re: Broken Link
    ... If he's your client, he hired you presumably because you know more about scheduling than he does. ... So how can you offend him by giving him what he is paying for and explaining the correct way to plan the project? ... John wrote: ...
    (microsoft.public.project)
  • Re: Broken Link
    ... dynamic plan is and what the fixed tasks are.So i am stuck figuring out ... including dynamic scheduling to your client or suggest that he/she take ... understood what a real dynamic plan is, you would both be better off. ...
    (microsoft.public.project)
  • Re: Email Client Recommendations
    ... (prior to which I had been only a part-time OS X user). ... Whenever I do try out an Email client, I do immediately look to how the ... You can certainly do that with Mail, Eudora and Thunderbird, and ... using IMAP with my Me account this year, and find it works far better ...
    (comp.sys.mac.system)
  • Re: Yet another Trenb / SBS2003 Question
    ... posting - and then prior to my little tweak of the Services mentioned above. ... I think you can pull the install from the client. ... click on the link to install Officescan. ... > If you're prompted for an sbs domain username/password, ...
    (microsoft.public.windows.server.sbs)