Re: Outline Levels in Different Views
- From: "JulieS" <JulieS@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 15 Jul 2009 13:43:49 -0400
Great Stacy. I'm glad you were able to work out the trouble and
thanks for posting the details.
Julie
"Stacy" <Stacy@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:E897207E-479F-4F7B-BEA9-D83F6379B06E@xxxxxxxxxxxxxxxx
Hi Julie,
I am sorry for being so vague. I think I realized what happened
though. I
deleted a custom table but never took it off the view I was trying
to use.
Once I did that, I stopped getting the message and now I can
expand/collpase.
Sorry about that but I think it is all set!
Thanks,
Stacy
"JulieS" wrote:
Hi Stacy,
Thanks for the information that you're on Project 2007. I've not
personally seen what you mention and I couldn't find any other
posts
with the problem you note, so, let' get a bit more detail and see
if
we can work this out.
If I understand, you've created some custom tables and views in
Project 2007. Please provide more detail about the custom views
you've created -- do they include filters of some sort? You said
you get a message when attempting to switch back to the standard
Gantt view -- please tell us specifically what the message says.
Does the message occur with all project files or just one
specifically? If it is just one file, it's very possible that
you
have a corrupted file and the problem with the views is a symptom
of
that corruption.
Let us know more details -- what customization are you doing,
what
views, what error messages and we'll see if we can reproduce
here.
Julie
"Stacy" <Stacy@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:48C3F209-B3DC-48FD-B7AC-2A35B777B53E@xxxxxxxxxxxxxxxx
We are on MS Project 2007 (client version not server) Service
Pack
2
"JulieS" wrote:
Hi Stacy,
What release of Project, including service packs are you
using?
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"Stacy" <Stacy@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:58E5FA53-531A-4F8F-8388-D5D979CE9845@xxxxxxxxxxxxxxxx
Hi Julie,
I am not sure if your solution addresses a similar issue I
am
having. So, in
the normal Gantt/Entry view I have collapsed some outline
levels.
I go and
create some custom tables and views but when I try to go
back
to
the normal
Gantt/Entry view, MS Project will not allow me expand the
sections
again. It
is like they are frozen and I get a message that refers to
my
custom view and
I have to delete my custom view in order to get the expand
and
collapse
functionality again. Does this make sense or have you seen
this?
.
- References:
- Re: Outline Levels in Different Views
- From: Stacy
- Re: Outline Levels in Different Views
- From: JulieS
- Re: Outline Levels in Different Views
- From: Stacy
- Re: Outline Levels in Different Views
- From: JulieS
- Re: Outline Levels in Different Views
- From: Stacy
- Re: Outline Levels in Different Views
- Prev by Date: How to add Activity Definition
- Next by Date: Re: How to add Activity Definition
- Previous by thread: Re: Outline Levels in Different Views
- Next by thread: Flag and text fields
- Index(es):
Relevant Pages
|