Re: Third party Integration - How to Map Fields in MS Project?

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Hello Sharjeel,

Are you mapping your data to the Actual Start fields or the Start
fields in the map? As you note, when updating Actual Start and
Actual Finish, the Start and Finish fields will change to match the
Actual dates. Are you saying that when you update Actual Start you
are not seeing the Actual Start value stay in Project?

Give us a bit more information about your map definition and we'll
try to be more helpful. Please also let us know what version of
Project (2003? 2007?) including service pack you are using.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project


..
"Sharjeel" <Sharjeel@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:301A3EA0-71A1-4E4A-B2CA-024B17A1E95C@xxxxxxxxxxxxxxxx
We have a Basic Task management system, with task id, description,
work,
planned & actual dates. We want to synchronize this with MS
Project. I am
able to map most of System's fields with MS Project.
The problem comes when i am trying to update 'Actual
Start/Finish/Work'
fields. Instead of updating those fields it actually updates
'Start/Finish/Work' fields.

When i do it manually it updates both ( that is fine as I have set
the
Baseline ).
But programmatically i am not able to achieve the same.

Any help would be appreciated..







.