Re: % Work Complete 'Variance'



Andrew and Jim thanks very much to both of you for your. You don't know how
much i appreciate this help.

Andrew:
The first time u suggested using the custom formula i was actually looking
for a built in column such as '% Work Complete' that will serve my purpose.
But seems like it does not exist. So, I have decided to use Projects EVM
functionalities and the advantages it will provide like u have described.

Jim:
Following you suggestions i have have started using the 'Physical % Complete'.
For this purpose in new project plans i am assigning Standard Rate of $1 for
all resources and assigning those resources to all tasks. After that i have
saved a baseline and from Tools > Options > Calculations, i have changed the
'Default Task EVM' to 'Physical % Complete'.
From then on, for tasks that are 100 % complete, i am setting their
'Physical % Complete' to 100%.

Will you please confirm that the right process has been followed (to solve
the problem this post is about)?

....

I have another question:
What do i do for projects that already have a baseline created and Actual
values (Work, Start/Finish dates) entered?
To answer this question I downloaded the white papers from your blog
regarding % Complete and came to conclusion that if i entered the Baseline
Work value in the corresponding Baseline Cost column (after assigning $1
standard rate to resources), i will be set up to solve the problem i was
discussing at the beginning of the post.

Do you agree?

"Andrew Lavinsky" wrote:

I think we're all pretty close. The question is whether you want to use
Project's native EVMS functionality with its reporting and timephased
tracking - or create a custom field which doesn't tie into the out of the box
reports, and wouldn't be timephased.

If you assign the $1/hr resource rate, you could use EVMS easily.

If not, I still think you could achieve the goal with a custom formula of
"([% Work Complete] X [Baseline Work])/60." If you are updating actual and
remaining work regularly, that will get you the number you seek.

Shahriar - why would that not work?

-A

.



Relevant Pages

  • Re: Leveling -- How best to set up a production support team?
    ... I still think the day per day granularity for the baseline work beyond ... >> you would use generic resources after that. ... >> It seems a bit overdone to me to try to plan generic resourcs on ... > I am using generic resources only when estimating the effort required ...
    (microsoft.public.project)
  • Re: BCWP and BCWS
    ... I did some reading of past comments and saw resources that were assigned need ... You are using solely fixed costs and as such, ... of the task reports to add those fields. ... No you shouldn't save a new baseline. ...
    (microsoft.public.project)
  • Re: Actual Work Greater than Baselined Work
    ... it often is necessary for project resources to work more ... circumstances necessitate applying more effort than planned to get a task ... work hours defined by the resource's working time calendar but work covered ... A task's Actual Start and Finish are different from Baseline ...
    (microsoft.public.project)
  • Re: % Work Complete Variance
    ... If you do not use resources, just make a generic resource "Worker" at $1/hr ... Work and cost become synonamous. ... One way I can think of doing this is manually by adding up the baseline work ... Assumption - no matter what it actually takes to complete this task (1 hour ...
    (microsoft.public.project)
  • Re: Post Project Analysis
    ... We created the schedule using MS Project; Resources were assigned, ... Then we set a baseline ... Project 2007 to perform 'Post Project Analysis'? ...
    (microsoft.public.project)

Quantcast