Michael,

This is good news. People often like to think that manual is best. That viewpoint can be right when done with enough complexity so as to not fool one's self. The trick is that it's easy to get fooled.

Hopefully at this point you can convince the planning staff to start again and build the schedule model/estimate in Project (or equivalent). In addition to providing some aids for dealing with the schedule complexity, this approach will get you to one plan in which you can focus on the plan instead of focusing on two plans and then having to resolve differences.

And: for so many reasons, don't try to schedule with "as late as possible" tasks using backward planning. do it on a forward-planning basis ... develop a plan for which Project computes the completion dates with "as soon as possible" tasks within your deadlines. If you don't like the computed dates, change the plan.

--rms
.



Relevant Pages

  • Re: Rebuidling a paper/pencil schedule in MSP2003
    ... That viewpoint can be right when done with enough complexity so as to ... Hopefully at this point you can convince the planning staff to start ... again and build the schedule model/estimate in Project. ... focus on the plan instead of focusing on two plans and then having to ...
    (microsoft.public.project)
  • Re: Proper Leveling Techniques - Rescheduling to start later
    ... Start and Finish are what your schedule calls ... Baseline Start and Finish are your original starting plan ... otherwise to force the tasks to end up on certain dates - leveling has ... I don't know why you're so adament againt using SNET constraints in any ...
    (microsoft.public.project)
  • Re: Finish Date Auto Update
    ... I work for a door company who gives out ... want in that field and then they are always on schedule. ... > The check boxes you're referring to don't have any effect on that behavior - ... But if it deviates from the scheduled plan they MUST manually ...
    (microsoft.public.project)
  • Re: Finish Date Auto Update
    ... The engineers out doing the jobs are not project managers even though they may have supervisory duties on the job site. ... Project planning, managment, and monitoring is more appropriately the role of the supervisor's supervisor. ... want in that field and then they are always on schedule. ... But if it deviates from the scheduled plan they MUST manually ...
    (microsoft.public.project)
  • Re: Bring Past Planned Work Current
    ... How could it ever be possible to pull work that's behind schedule forward and NOT have the finish date change??? ... Unless the scope of the project changes so it essentially becomes a different project, the original baseline should be engraved in granite and never changed. ... The baseline is a fixed reference point for monitoring progress of actual against plan and is the sole source of information you have as to whether your plan as it is evolving once work is underway is on-time or within-budget. ... If work has been delayed so the current schedule shows you finishing 1 October, that unchanging baseline is your only record that your original plan called for you to finish 1 September and now you're a month late. ...
    (microsoft.public.project)