Re: Master Snapshot Linking/Unlinking

Tech-Archive recommends: Fix windows errors by optimizing your registry



Ok. I created my resource pool and saved it to my harddrive. Now, I am
creating a separate project. I want to use resources from my pool. But, when
I go to "share resources" the dialog box doesn't give me an option to share
any things. Any ideas what I did wrong here?



"Rod Gill" wrote:

Personally, I never ever create resource pools or linked consolidated files.
I only do unlinked consolidated - for executive reports and resource
levelling. I I really need a Resource Pool to level resources I create one
temporarily, then dismantle once I've finished. If you use the C: drive make
sure all files are on the C: drive.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"avimia" <avimia@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:C24D7821-A647-443A-8C11-1D200793969A@xxxxxxxxxxxxxxxx
Hi Rod,
And thank you for the great explanation on the resource pool. I have
already
started making my first resource pool, inputting just the people's names,
etc
and saving it just "pool".

I do understand keeping all these files on the same drive. So please allow
me to do a "dry here" to see if I have it right:
Let's say I have projects #1, 2, 3 and 4 and my resource pool file.
Normally, I save those to my C drive. And then I can create a master with
1,
2, 3, 4 and pool as sub-resource. I will "link" those so I can do
"dynamic"
changes on a constant basis. Then, when the Executives need it, I can
create
a separate master UNLINKED (as a snapshot) or do some printable reports.

Does that sound like I'm on the right track?

As long as I know I'm on the right path, I know that I will be able to do
all the right steps... but... save all my files to my folder on the "N
drive"
on our network.

Thank you again for your help. It's very appreciated!
avimia



"Rod Gill" wrote:

Hi,

I strongly recommend keeping master projects and resource pools in the
same
drive as the projects. This should significantly reduce corruptions due
to
network glitches.

To create a Pool, simply list all resources, rates calendar details etc
in
one project and save to same drive as other projects. Do not use the
master
or enter any tasks into it.

Open other projects then share resources. Save BOTH as only saving one
rolls
the dice again.

Be VERY very careful of linked files: corruptions can happen one week,
yet
take several weeks before the problem appears. In the mean time, your
backups are full of corrupted versions, which is why I strongly recommend
not linking and using new master projects each week.

Save Views, tables etc to Global.mpt using the Organizer and printing etc
is
easy.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"avimia" <avimia@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:FE6DCB1E-BEEF-4EA6-93AF-FAC4FA15B88C@xxxxxxxxxxxxxxxx
Hello all,

Wow! thank you for the wonderful input. This helps me tremendously.

It also leads me to 2 new questions please:

1.) I understand being extremely careful of renaming/moving/deleting
files
so not to mess up my master. However, I'm also a huge fan of
backup/backup/backup. Now... fortunately... we have a full blown IT
department with tons of backups and redundancy. So... my question is
this:

?? When I create my new master, or each day when I am working in it or
my
subprojects, and I go to save it... am I ok to save it directly to my
(own)
folder on the network (I can protect the file so no one can get it in
it).
just wondered if Project will let me save it any other place than on my
own
harddrive.

Ok, so on to my last question: And, please pardon my ignorance. But,
what
is
the quickest way to create a resource pool? I have looked and looked
through
all the help files and it just doesn't quite make sense. I am asking if
there's a quick way to do this because you have to remember that I have
not
YET built any of the projects or the master. So, I don't have any
resources
put in to anything yet. Is it possible to just create a new project and
just
put all my (human) resources in to it and use it as my "pool"? I ask
because... there will be over 50 different people I have to list (ug).

I truly appreciate everyone's help. I am ol' pro at project management,
but
I'm still new to the whole MS Project thing.

Thanks again,
avimia



"Rod Gill" wrote:

My usual caution here:

Links between master and sub-projects, projects and resource pools are
fragile. Anytime you rename, move or over-write any of the files
without
first breaking the link and you throw the dice. It's when, not if you
get
one or more file corruptions. I've also now found that any network
glitch
can also cause a problem.

In your scenario, why not create a new master file each week but when
you
inert each project clear the Link option. Now all data is copied to
the
master (no link) and all resource data is automatically consolidated.

Make this even faster by recording a macro of you doing this manually.
Make
sure the first recorded instruction is file,new!

As projects finish, simply delete the line of code for that project:
easy!

These snapshots also provide a great audit trail over time as well.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com



"avimia" <avimia@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:1F7BA80A-B835-4857-BAB3-72E08D753370@xxxxxxxxxxxxxxxx
Hello experts,

These questions relate to doing a master project linking/unlinked
(snapshot).

My scenario and questions are this:

1.) I am going to have to create a master project with about 25
sub-projects
within it at any single time (sub projects will fall off after
completion).
Most all the projects will have shared (human) resources. I am using
Project
Pro 2007 (no server). I am the only person managing it all. At this
point,
I
am thinking that inserting and LINKING the subs into the master will
be
the
best solution (in helping me with the constant updates to each sub).
However,
having the foresight to know the Executives will really only need a
"snapshot" during their meetings (which is normally weekly), this
means
I
do
NOT need to do a linked master/sub set up. This is especially the
case
since
each week, I am required to email the updated "report" for them to
see
each
week (before their meetings). So, I'm trying to understand how I can
accomplish both scenarios. So:

?? - Is it a situation where I will create my inserted/LINKED set
up,
but
then once-a-week re-do (something?) to create only a snapshot for
the
meetings?


2.) This deals with "archiving" my sub projects. As I mentioned
above,
my
master list (linked) will have about 25 sub projects going on at any
one
time. And, as the projects are completed, I want them to "fall off"
my
Master
(so that 5 years from now, I don't have a bloated system).
However... I
can
also see the importance of having "historical" data as it will never
fail
that a "finished" project will need to be reviewed for whatever
reasons.
So,
I'm trying to understand how/what is the best way to save/archive
those
projects which are completed and will "fall off". Any ideas are
greatly
appreciated.

Thank you!
avimia
archives






.



Relevant Pages

  • Re: using resource pool with master project
    ... currently using as the Master and then renamed the ... more subprojects. ... If you stop sharing the resource pool file to the master project, ...
    (microsoft.public.project)
  • Re: Master Snapshot Linking/Unlinking
    ... you need to open both the resource pool and the ... I I really need a Resource Pool to level resources I ... Microsoft MVP for Project ... a separate master UNLINKED or do some printable ...
    (microsoft.public.project)
  • Re: New default, global.mpt
    ... "Rod Gill" wrote: ... Author of the only book on Project VBA, ... as part of your Resource Pool as any default assignments will immediately ... open the Resource Pool as option 3 "Open resource pool... ...
    (microsoft.public.project)
  • Re: adding Resource Pool on existing plan
    ... resource pool seems to confuse things so I am giving that up. ... Open the resource pool (read-only if others have to have simultaneous ... The project managers give me their plans to incorporate in the Master plan. ...
    (microsoft.public.project)
  • Re: Master Snapshot Linking/Unlinking
    ... And thank you for the great explanation on the resource pool. ... a separate master UNLINKED or do some printable reports. ... This deals with "archiving" my sub projects. ...
    (microsoft.public.project)