Re: Arithmetic sum of subtasks
Is it possble you can show an example of how to use the custom duration
field to calculate the sum ofsubtask durations ?
Thanks.
"Dale Howard [MVP]" wrote:
RakeshK --
What you are seeing in Microsoft Project is correct. The Duration of any
summary task is NOT the sum of the Durations of the subtasks. The Duration
of a summary task is calculated from the Start date of the earliest starting
task to the Finish date of the latest finishing task. But if you absolutely
need to calculate a custom Duration as the sum of the subtask Durations, you
would need to create a custom Duration field for this purpose. Hope this
helps.
--
Dale A. Howard [MVP]
VP of Educational Services
msProjectExperts
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We write the books on Project Server"
"RakeshK" <RakeshK@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:D54BC069-FA12-43A9-B7DF-C4D97C299432@xxxxxxxxxxxxxxxx
Hi,
Presently the duration of a summary task is NOT the arithmetic sum of the
durations of its subtasks. It is calculated as the difference between the
most end date and the least start date of the subtasks.
How can i show the arithmetic sum of duration of subtasks in a summary
tasks ?
Please help.
.
Relevant Pages
- Re: problem setting task days & subtask hours
... The duration of a summary task is the time between when the earliest starting subtask begins and the latest finishing subtask ends. ... I have 1 task with 6 subtasks that are to be completed in 1 day. ... The WORK column has hours allotted to the 6 subs and totals correctly. ... (microsoft.public.project) - Re: calculate summary start and finish using pert anayst
... That's exactly the way Project functions EXCEPT that summary task durations are read-only fields calculated based on the durations of their child subtasks and will not accept direct user input. ... So when you list each summary's children, set up the dependency links between them, and enter their durations, the summary task's duration will be calculated. ... PERT is a method of calculating task duration based upon Optimistic, ... (microsoft.public.project) - Re: problem setting task days & subtask hours
... Duration of a summary task is based on the difference between the finish date ... the subtasks are not sequenced then the start date of the summary ... The total time for all subtasks totals ... (microsoft.public.project) - Re: Deadline works opposite to how it should
... Summary task durations are always calculated values, determined by the time from the earliest starting subtask to the latest ending subtask - as such they are read only and cannot be manually updated, nor will they always change in response to a subtask's duration change since they're not a simple arithmetic sum. ... Links, leveling, constraints, or anything that causes the subtasks to run other than in parallel may change the specific numbers but the principle of the behavior will remain - the duration of a summary task is number of working time calendar time units between the point when work is first done on any one of its component subtasks until the last bit of work is performed on any one of the subtasks. ... (microsoft.public.project) - Re: problem setting task days & subtask hours
... indicates that the Duration is an estimate, and 1 Day is the default. ... The hours column is totaling correctly, but the duration column simply ... I have 1 task with 6 subtasks that are to be completed in 1 day. ... Duration of a summary task is based on the difference between the finish ... (microsoft.public.project) |
|