Re: Critical path not showing through an activity with ed days

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



An activity with a positive, non-zero slack time is by definition non-critical. You keep saying the task is question is critical but by the formal definition of a critical task, it isn't. It could be delayed by up to 0.63 days before it becomes critical and begins to push on the successor task's start time.
--
Steve House
MS Project Trainer & Consultant

"Andrew" <Andrew@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:690723B8-B065-459D-89BE-D451C1EF6F58@xxxxxxxxxxxxxxxx
Gerard

I see. My activity (ed) ends at 17:00 and the next starts at 08:00 the next
day I checked the Total float and the ed act has 0.63ed. This leads to a
further question if I run a critical filter the ed activity will not be
selected, and a gap is shown between the critical activities with no links
between them - is there any way to show the ed activity as critical, or would
it be better to allocated a 7 day calendar to the cure activity.

Andrew
"Gérard Ducouret" wrote:

Andrew,
- the curing activity ends on a Thursday : at what time ? with ed duration
it could drift until Friday morning 8am
- and the following activity starts on the friday : At what time?

Gérard

"Andrew" <Andrew@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message de news:
039AB6BA-D5E5-498A-9D8E-2B783007B3A6@xxxxxxxxxxxxxxxx
> Gerard
>
> Firstly thankyou for your quick response. I understand what you are > saying
> regarding the weekend, however the curing activity in this case ends on > a
> Thursday, and the following activity starts on the friday and is not
> linked
> to any other activity. I quickly opened up a new project and tried the
> same
> thing and the ed activity is still blue (non critical).
>
> Andrew
>
> "Gérard Ducouret" wrote:
>
>> Hello Andrew,
>>
>>
>>
>> These tasks with elapsed duration can run 24/7. May be this "Concrete
>> curing" task ends on Friday evening at 5pm. Its successor with >> classical
>> duration cannot start before next Monday, in the morning (may be 8 >> am).
>> But,
>> if necessary, the concrete curing could drift on Saturday and on >> Sunday,
>> without postponing the following task. So this ed task as some slack
>> (almost
>> 2 days)
>>
>>
>>
>> Gérard Ducouret
>>
>>
>>
>> "Andrew" <Andrew@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message >> de
>> news:
>> B32D7303-0620-4CFA-868F-FADF6B72CC02@xxxxxxxxxxxxxxxx
>> >I have an activity - concrete cure which I have alloted 7ed. I know >> >that
>> >this
>> > activity is critical because I have linked it to be. However, the
>> > critical
>> > path jumps this activity ie its blue and the next activity is red. >> > Any
>> > ideas
>> > ??
>> >
>> > Andrew
>>
>>
>>




.



Relevant Pages

  • Re: OT:From the Decider to the Blamer
    ... President George W. Bush from 2001-04. ... So Andrew your saying that everything is ok with the obama ... I am surprised at you Andrew, I expect someone like little eddie to ...
    (rec.music.classical.guitar)
  • Re: OT:From the Decider to the Blamer
    ... President George W. Bush from 2001-04. ... So Andrew your saying that everything is ok with the obama ... I am surprised at you Andrew, I expect someone like little eddie to ...
    (rec.music.classical.guitar)
  • Re: OT:From the Decider to the Blamer
    ... President George W. Bush from 2001-04. ... Politics and Public Policy at Georgetown University". ... So Andrew your saying that everything is ok with the obama ...
    (rec.music.classical.guitar)
  • Re: Why are Sox fans in denial? (Give the guy a break)!)
    ... Andrew wrote: ... The only people giving him any benefit of doubt are Red Sox fans in ... How about he's telling the truth - it was an honest mistake. ... *not* saying he didn't do something wrong, ...
    (alt.sports.baseball.bos-redsox)