Re: Where to put tasks that cannot be scheduled yet?



You don't schedule the work on tasks, MS Project does. It's job is to tell you when you ought to be doing the work - let it do its job. Update the tasks that have been completed with actual date where they were done. Link your tasks into a proper dependency relationship where it applies. Assign your resources. Run the resource leveling tool to resolve the overallocations. Project will schedule the tasks still to be worked for you, placing them on dates that gets the project done soonest. Go the the resources and tell them those are the dates they need to be doing these tasks.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs




"Burnley81" <Burnley81@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:699EE7E2-AD64-48B9-B92F-27C5786AD98F@xxxxxxxxxxxxxxxx
I have plenty of project plans - and one I have if basically a odd jobs plan.
I have tasks in there where most are scheduled - a few though have no dates
- everything else is complete for these tasks, resource, duration etc.
Currently they sit at the start of the plan - dated 01/01/09.
Unfortunately the resource usage shows them as being over allocated in work
on this day. I cannot have this as the Master Plan must not show over
allocation.

The only way I can find at present to overcome this is reduce the duration
to "0" and put notes in the Task Allocation for the real duration - so that I
can update when it does come to scheduling this work.
Is there an easier way of not scheduling work - and not affecting resource
allocation?
Thanks


.



Relevant Pages

  • Re: Formula Questions
    ... Start date and then that value is divided by task duration. ... we have many schedules with only one resource ... We baselline that and use SPI as described ... becomes important as it gives you ahead or behind schedule. ...
    (microsoft.public.project)
  • Re: I cant make hammock tasks work
    ... I wonder what it is you're seeing when you say it's changing duration when you add resources. ... But if I have "Carpenters" assigned to the task at 200% and I edit the units to 300%, as far as Project is concerned I haven't really added a resource. ... Do you by any chance have it set to schedule from project end date forward? ...
    (microsoft.public.project)
  • Re: 24 hour calender 7 days a week in 3 team shift
    ... So when you say a task has a duration of "1 day" ... Steve House ... We also want to show what kind of resource % that is needed. ... Project's task list and calculated schedule to determine that an A&P ...
    (microsoft.public.project)
  • Re: Buffer or lag periods
    ... LOL - John and I are on opposite sides of the philosophical fence on this one - I am strongly opposed to ever using fixed duration scheduling except in very specific circumstances. ... The assumption is that if the task will take longer than you want it to, making the resource work harder will solve the problem and make the task fit into the time you want to allow for it. ... But it won't work - in a well managed firm resources are always working as hard as they're ever going to work so if it's going to take him 3 days to polish 100 fids, it will take him 3 days no matter what your schedule calls for, whether you've budgeted 10 days or 1 day. ... My prob is, when i create my plan, i only know the ...
    (microsoft.public.project)
  • Re: resource underallocation
    ... and it would nicely "Gantt Chart Style" show availability odf the resource. ... Project's leveling to actually create the assignments to MISC, ... in the schedule in the event the resource is overallocated at the time ... working is the remaining allocation. ...
    (microsoft.public.project)

Quantcast