Planned work at specifiec dates shifted when actuals arrive
- From: Everc <Everc@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 28 Jan 2009 12:50:01 -0800
For the holidays we use a specific pattern for each assignment. For example
assignment1 takes holiday in first week of april. We put in the task
'holiday' for each day 1 day work in the right pane at task usage view
(planned work). This is initialy done for everyone. This is a pattern that is
seen as 'countered' in the colom 'work contour'. The icon with the pencil is
show in the indicators colom.
Work is planned at fixed days, leveling goes around it. Everything ok until
we take in actuals from PWA.
When actuals is pulled in and the pattern divers from the planned one,
project shifts the manually edited work towards the future. Without a logical
reason.
Who knows what the reason is?
.
- Follow-Ups:
- RE: Planned work at specifiec dates shifted when actuals arrive
- From: Mike Glen
- RE: Planned work at specifiec dates shifted when actuals arrive
- Prev by Date: Resource Pool - Slow
- Next by Date: Adding new tasks always has constrant "Start No Earlier Than" - W
- Previous by thread: Resource Pool - Slow
- Next by thread: RE: Planned work at specifiec dates shifted when actuals arrive
- Index(es):
Relevant Pages
|