RE: Milestone Duration Mystery

Tech-Archive recommends: Fix windows errors by optimizing your registry



Jim,

Thx for the response.

Sorry about not providing enough info, frustration setting in <grin>. This
is 2007 with SP1 and all updates except for the December update.

I have seen this behavior off and on for some time now and thought it was
poor scheduling by a select set of PMs. However, a PM that I know is very
good with his schedule witnessed this and told me that after I pointed out
the issue he added the resource back to the task and the duration returned to
zero, when he again removed the resource the duration jumped to over a 1000
days.

I have not been able to repeat this behavior in a test schedule. I can only
speculate that it may come from some of the schedules that were migrated from
the 2003 server and people are copy and pasting old corrupted tasks into new
shcedules. Anyways, I am waiting for the next time it happens to be able to
see the change take place as witnessed by the earlier mentioned PM.

Darrell

"Jim Aksel" wrote:

MS Project 2003 is on SP3
MS Project 2007 is on SP1 plus some additional updates
Make sure you are up to date. If the problem persists, let us know
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Darrell" wrote:

I have not been able to find an answer to this so I will ask again.

I have seen several project schedules from several different project
managers where a tasks duration suddenly jumps out into the future without
anyone knowing why. I just worked with a PM who removed a generic resource
that was mistakenly assigned to a milestone and when the generic resource was
removed the duration changed to 1000 something days and the finish date went
to 2049 even thought the task had zero duration and zero work and zero
progress prior to removing the resource. What is causing this behavior?

Darrell
.



Relevant Pages

  • Re: Are Fixed Duration tasks flawed?
    ... If I have 2 carpenters and list them in my resource definitions as ... Bill Carpenter and Joe Carpenter, each available 100% I have 2 resources. ... Fixed Duration / W=D*U holds true for the whole. ... sense and is predictable enough to use for detailed schedule planning. ...
    (microsoft.public.project)
  • Re: Formula Questions
    ... Start date and then that value is divided by task duration. ... we have many schedules with only one resource ... We baselline that and use SPI as described ... becomes important as it gives you ahead or behind schedule. ...
    (microsoft.public.project)
  • Re: I cant make hammock tasks work
    ... I wonder what it is you're seeing when you say it's changing duration when you add resources. ... But if I have "Carpenters" assigned to the task at 200% and I edit the units to 300%, as far as Project is concerned I haven't really added a resource. ... Do you by any chance have it set to schedule from project end date forward? ...
    (microsoft.public.project)
  • Re: 24 hour calender 7 days a week in 3 team shift
    ... So when you say a task has a duration of "1 day" ... Steve House ... We also want to show what kind of resource % that is needed. ... Project's task list and calculated schedule to determine that an A&P ...
    (microsoft.public.project)
  • Re: Buffer or lag periods
    ... LOL - John and I are on opposite sides of the philosophical fence on this one - I am strongly opposed to ever using fixed duration scheduling except in very specific circumstances. ... The assumption is that if the task will take longer than you want it to, making the resource work harder will solve the problem and make the task fit into the time you want to allow for it. ... But it won't work - in a well managed firm resources are always working as hard as they're ever going to work so if it's going to take him 3 days to polish 100 fids, it will take him 3 days no matter what your schedule calls for, whether you've budgeted 10 days or 1 day. ... My prob is, when i create my plan, i only know the ...
    (microsoft.public.project)