I am in the Gantt Chart view and the "adjust to" option is grayed out. There
is nothing in the box. I did change the view several times but the only view
that allowed me to adjust the scale was "leveling Gantt". Is the adjust
scale option only available on certain views? I do not work in Project so I
am not familiar with it. Thank you for your help.


--
Stella Rivera


"JulieS" wrote:

Hello Stella,

Pardon me for bumping in. What view in project are you attempting
to print. Is there anything in the "adjust to" settings box? Can
you enter 100 in the box?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Stella Rivera" <StellaRivera@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:9402F6A0-3475-47D7-98F9-8CF0E5A4205B@xxxxxxxxxxxxxxxx
Hello Mike,
I went to the FAQs before I posted my question. Nothing that is
recommended
worked when I tried it. THe tabs are disabled for some reason and
when I
click on them I get the box that says to enter a value between 10
and 500.
The document doesn't appear to be protected and I don't know what
else to
try. The document is in Project 2003. Appreciate any other
suggestions.
--
Stella Rivera


"Mike Glen" wrote:

Hi Stella,

Welcome to the Microsoft Project newsgroup :-)

First, please see FAQ Item: 44. Printing Problems

FAQs, companion products and other useful Project information can
be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on:-)

Mike Glen
Project MVP

Stella Rivera wrote:
I am unable to change the scaling. I cand do a print preview.
When
I go to the page setup the only thing I can change is the page
orientation. When I click on the margins or view tabs a box
appears
and states "the value must be between 10 and 500". What value,
where
does it go? Why are the tabs disabled? I appreciate any help.






.



Relevant Pages

  • Re: Unable to change scaling
    ... Just so we are talking about the same thing, you open the Gantt ... that allowed me to adjust the scale was "leveling Gantt". ... I went to the FAQs before I posted my question. ... When I click on the margins or view tabs a box ...
    (microsoft.public.project)
  • Re: Unable to change scaling
    ... Stella Rivera ... that allowed me to adjust the scale was "leveling Gantt". ... I went to the FAQs before I posted my question. ... THe tabs are disabled for some ...
    (microsoft.public.project)
  • Re: Unable to change scaling
    ... allowed me to put a number in the box is the leveling Gantt view. ... that allowed me to adjust the scale was "leveling Gantt". ... I went to the FAQs before I posted my question. ... When I click on the margins or view tabs a box ...
    (microsoft.public.project)
  • Re: Unable to change scaling
    ... Stella Rivera wrote: ... that allowed me to adjust the scale was "leveling Gantt". ... I went to the FAQs before I posted my question. ... When I click on the margins or view tabs a box ...
    (microsoft.public.project)
  • Re: Can you shift an entire programme by a set amount in MS Project?
    ... Try the Analysis toolbar and select Adjust Dates. ... FAQs, companion products and other useful Project information can be seen at ...
    (microsoft.public.project)