Swapping Resources ?

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Hi all,

I have 2 resources, Jim and Mike.

Mike makes $20/hr and Jim makes $40/hr. The work for my task is 10days. If
I assign Jim to the resource and let him work 1day, I will have 9days of work
remaining.

If I then remove Jim and assign Mike to the task, I get a dialog box stating
"The Selected Item has some actual values. Do you still want to delete it?
Yes, No. If I select Yes, it removes the work that Jim did in lieu of
placing Mike on the job with 9days of remaining work which I believe should
be the expected behaviour.

What am I missing?
Glenn


.



Relevant Pages

  • Re: Swapping Resources ?
    ... When I replace Jim with Mike, both Jim and Mike are now shown in the Assign ... Try using the Assign Resources button. ... Project MVP ...
    (microsoft.public.project)
  • Re: 1 coach voted Cincy #1 ...
    ... 'The USA TODAY Board of Coaches is made up of 59 head coaches at ... Duke; Mark Dantonio, Michigan State; Butch Davis, North Carolina; Todd ... Southern Miss; Al Golden, Temple; Jim Grobe, Wake Forest; Jim Harbaugh, ... Richt, Georgia; Mike Riley, Oregon State; Rich Rodriguez, Michigan; Nick ...
    (rec.sport.football.college)
  • Re: Swapping Resources ?
    ... If you've recorded 1 day of actual work for Jim, ... see Jim's work for 1 day and Mike assigned to the remaining 9 days. ... information about Microsoft Project ... Resources dialog as being checked. ...
    (microsoft.public.project)
  • Re: Swapping Resources ?
    ... Sure that makes sense but if Mike is replaced by Jim and both Mike and Jim ... Resources dialog box. ... After replacing Jim with Mike, shouldn't Jim's name no longer be ...
    (microsoft.public.project)
  • Re: Swapping Resources ?
    ... I assign both Jim and Mike to the same task and I then have them both do one ... How can I remove a resource without ... Sure that makes sense but if Mike is replaced by Jim and both Mike ... Try looking at the Task Usage view to see what is going on -- ...
    (microsoft.public.project)