Re: Best way to account for departmental overhead?

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



Send me an email (go to my blog) wih your boss's info and I will put in a
good word for you
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Darrell" wrote:

Woo hooo... I have a method!! How do I send a link to this post to my Boss???
<grin>

"Jim Aksel" wrote:

As you can see, Darrell has come up with the "reciprocal solution" Both work
fine. The easy way to avoid Fred [80%] on the Gantt bars is to use the
Darrell Method.

If you want to use my method, place the resource name in the Initials Field
on the Resource Sheet. Then Format/Bar Styles and change the bar to show
Resource Initials rather than Resouce Name. So, you just fake it out.

You can let Barney work 40% of 80% by making his availability 0.8*0.4 =0.32
on the resource sheet
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"michael.franke@xxxxxx" wrote:

Hi Jim.

Thanks for your quick reply. Setting the max units does indeed get
the desired result. However, I'd like to treat 80% availablilty as
"full time" -- for display purposes at least. That is, the bar in the
Gantt chart next to Fred's task will say "Fred[80%]", which is
accurate but cumbersome.

Furthermore, there are some resources who I'd like to schedule at less
than "full time" -- like 50% -- that is, 50% of 80%, which is 40%.
Does that make sense? Essentially, I'd like to treat the 20% overhead
as a buffer, and hide it from the project except for calculations like
"5 days = 32 hours".

Also, if I'm doing things like this, do you suggest entering tasks in
terms of their "Work", or their "Duration"? Seems like it takes a
particular mind set, and being consistent would be key. Not to
mention the fact that if I enter a "Work" number, the "Duration" field
has a question mark (estimated) by default -- which doesn't make
sense, and makes me nervous.

Mike

.



Relevant Pages

  • Re: Best way to account for departmental overhead?
    ... If you want to use my method, place the resource name in the Initials Field ... on the Resource Sheet. ... Jim Aksel, MVP ...
    (microsoft.public.project)
  • There Is More To Mens Rights Than Soc.men
    ... http://www.mens-links.net/home.asp MRA Links Resource ... Google Marriage Strike ... Each blog has a section of MRA links, ... Excellent series of 4 articles on how Anglo and Western Women screwed ...
    (soc.men)
  • RE: BCWS, BCWP & ACWP give all or nothing
    ... Go to the Resource Sheet. ... Jim Aksel, MVP ... I did what you said in the Task Usage View and the Baseline numbers look ... I even added the ACWP field in that view and it ...
    (microsoft.public.project)
  • Re: custom columns for WKS
    ... please consider rating it. ... Jim Aksel, MVP ... Blog: http://blogs.catapultsystems.com/epm ...
    (microsoft.public.project)
  • Re: urget help about data report and ADO
    ... Chris Hanscom - Microsoft MVP ... Veign's Resource Center ... Veign's Blog ...
    (microsoft.public.vb.database)