Spreading the workload to assigned resources of a task




Hi!

I've opened a new project and added one fixed work task in which I've
entered that it needs 1080 hours of work to be completed (135 days). To this
task I want to add eight resources, four 100% and four 50%. The project
calenders is adjusted with christmas holidays, and the individual resources
have their calender adjusted with their days off.

Now, I'd like MSP to divide the work and calculate the duration so that all
resources will work every day until the work is completed. But MSP just
divides the work with the numbers of assigned resources, without caring of
the assignment reat (100% or 50%). So, each resource is assigned with 1080 /
8 = 135 hrs of work.

This means that the resources that is assigned 100% will finish earlier than
those with 50% assignment. And those with least time off for vacation will
finish first. ´

But I want MSP to calculate so that the amount of work is assigned so that
all will finish on the same day and the duration will be the shortest.

Can this be done?

Best regards

Mathias
.



Relevant Pages

  • Re: Spreading the workload to assigned resources of a task
    ... Ok, I thought MSP would do it automatically, but that did it! ... You could start with the task as fixed units and assign the resources at ... I'd like MSP to divide the work and calculate the duration so that all ... those with 50% assignment. ...
    (microsoft.public.project)
  • Re: Spreading the workload to assigned resources of a task
    ... You could start with the task as fixed units and assign the resources at the level you require. ... I'd like MSP to divide the work and calculate the duration so that all resources will work every day until the work is completed. ... This means that the resources that is assigned 100% will finish earlier than those with 50% assignment. ...
    (microsoft.public.project)
  • Re: Leveling How To
    ... From a business context standpoint it is a highly complex problem ... to simply bumping up his assignment and only a human expert - that's you - ... be done by next September without the increased resources anyway? ... Is there any way to get MSP to ...
    (microsoft.public.project)
  • RE: Spreading the workload to assigned resources of a task
    ... I think if you add the 4 resources allocated at 100% first and let MSP ... I'd like MSP to divide the work and calculate the duration so that all ... those with 50% assignment. ...
    (microsoft.public.project)
  • Re: Multiple resources, varying units
    ... When assigning resources to a 5 day fixed-duration task I ... The assignment units are calculated by work/duration = assignment ... I created the task and set it as fixed duration. ... last two people are allocated at 100% assignment units. ...
    (microsoft.public.project)