- From: "JulieS" <JulieS@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Mon, 8 Dec 2008 20:35:57 -0500
Hi cmulder,
The calendar view is quite limited as you've discovered. The length
of the bar (as with the Gantt chart) depends upon the task duration.
With 2 hour tasks, the bars are only going to be very small. I'd
really suggest trying the Gantt chart view.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
"cmulder" <cmulder@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:77EA916A-A3C6-480C-BC2C-3A00BCA2C3A8@xxxxxxxxxxxxxxxx
i am having trouble with calendar views too -- i have a project
with 4 tasks
per day, all starting at different times in the day -- most of the
tasks are
short (2 hours or so) and they all 4 tasks for each day show up on
the same
line on each day in the calendar -- and mostly, there is one
character of the
task name displayed (at very most -- sometimes no character at
all) -- how
can i change the format so that each task shows up on a different
line in the
cell for the day and also so that there are at least 6-8
characters of the
task name that can be read? thanks SOO much for your help!
"JulieS" wrote:
Hello Natascha,
You're welcome. Sorry to say this but to your new question --
no,
sorry again. The Calendar view has similar limitations in
Project
2007. You might try using the copy picture button to create a
gif
file of the calendar view and then printing the gif file to fit
all
tasks to one month, but the individual task coloring is still
going to
be a limit.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
"NAtaSchA" <NAtaSchA@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:5C95DACD-E784-4319-8A4F-D2D2FBF5B8BC@xxxxxxxxxxxxxxxx
Hi Julie,
thank you very much for the quick response!
Since both is not working with MS Project 2003 is there any
update
that I
can download? Or does any other MS Project Program (2007,
Standard
or
Professional) change colors of task bars individually and show
many
tasks in
one day in one month?
Thanks again,
Natascha
"JulieS" wrote:
Hello Natascha,
No, sorry to both. The formatting for tasks in the calendar
view
is
limited to what you can modify through Format > Bar Styles.
Instead
of
changing colors for resources, I'd suggest filtering the
calendar
view
to only show Fred's Task or only show Linda's tasks. You
cannot
color
bars individually in the Calendar view.
What you see printed in the calendar view can be *slightly*
modified
by dropping fonts but I sincerely doubt you'll be able to ever
20 tasks per day. The max seems to be around 6-8 per day.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
"NAtaSchA" <NAtaSchA@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message
news:1E250972-9A4A-4338-9350-2A62746A90BC@xxxxxxxxxxxxxxxx
Hi,
I have two questions regarding the CALENDAR VIEW of
Microsoft
Project 2003:
1) How can I color the task bars assigned to resources
differently?
eg
Resource Fred = Task Bar in blue; Resource Linda = Task Bar
in
red?
If this is not possible; Can I color each task bar manually?
2) How can I change the size of the monthly calendar, so
that all
my
tasks
(about 20 in 1 month) fit on the monthly calendar view
printed
***?
Thank you very much for your help,
Natascha
.
- Follow-Ups:
- Re: Calendar View of MS Project 2003
- From: cmulder
- Re: Calendar View of MS Project 2003
- References:
- Re: Calendar View of MS Project 2003
- From: cmulder
- Re: Calendar View of MS Project 2003
- Prev by Date: RE: Scheduling multiple resources on a task to finish quicker
- Next by Date: Re: % complete visual reports
- Previous by thread: Re: Calendar View of MS Project 2003
- Next by thread: Re: Calendar View of MS Project 2003
- Index(es):
Loading