I’m new to Microsoft Project, but I think I have a problem with how Project
schedules resources. My scenario is:

A task is estimated to take 300 hours to complete. I have three resources
assigned to the task. Resource #1 starts immediately, resource #2 in a week
and resource #3 starts in two weeks. All three resources are available to
work on the task to completion.

It looks like Project is assigning 100 hours to each resource and does not
consider the task complete until the last resource (#3) finishes their 100
hours, which will take two weeks longer than the first resource. This means
during the last week of the task, Project thinks resource #1 and #2 aren’t
working at all.

What I want to happen is Project automatically adjusts the hours for each
resource to get the earliest possible finish date. If the effort (hours) is
adjusted or resources take vacation or sick days, Project should re-adjust
and give me the new finish date.

I have worked around the problem by creating three separate sub-tasks and
assigning a different resource to each sub-task and then manually playing
with the hours for each resource to get the earliest finish date.

What am I doing wrong?

.



Relevant Pages

  • Re: Month by month resource leveling results in overallocated reso
    ... Your practice of assigning at a 70% level means that when you look at a plan that has Bill assigned to a task that shows a duration of 8 hours, starting Monday at 8am and ending at 5pm, it really means that Bill will work on it for 6 hours sometime between 8 and 5. ... But those records rarely detail hour by hour what the resource was doing - you know it took Bill about a week last year but you don't have a step by step record of his day, merely the fact he worked on it during the second week of March. ... should never have resources assigned to them, their priority settings are ... does the priority of the summary task affect it at> all? ...
    (microsoft.public.project)
  • Re: So many questions...so little time...on scheduling and leveling
    ... My advice is to use leveling. ... ALWAYS assigning a resource to a task at its max. units) leveling will give ... > Leveling produced a schedule that ran for years. ...
    (microsoft.public.project)
  • Re: automatic resource assignment
    ... Duration is 25 days, Work is 20 hours. ... Each has his own availability (due to hiring ... I would love to be able to tease Project into assigning tasks to ... based on the available time that each resource has. ...
    (microsoft.public.project)
  • Re: automatic resource assignment
    ... If you have a dozen pigeons and you throw them a bag of breadcrumbs and it ... I would love to be able to tease Project into assigning tasks to ... based on the available time that each resource has. ...
    (microsoft.public.project)
  • Re: Month by month resource leveling results in overallocated reso
    ... And what if a resource truly is only ... Your practice of assigning at a 70% level means that when you look ... (Though the priority explanation was as I expected it...thanks for the ... does the priority of the summary task affect it at ...
    (microsoft.public.project)