Re: Duration/Work



Hi Quixote,

Welcome to this Microsoft Project newsgroup :)

Where are you entering Work? Check Tools/Options.../Calculation tab and
ensure Calculation mode is on Automatic. When you enter a new tasks, they
will start on the Start Date of your project or on the current date
depending upon the setting selected in Tools/Optons.../Schedule tab - New
Tasks setting. You can select the 24 hours calendar in Project/Project
Information calendar setting - but remember, if you assign resources thet
will be required to work 24/7 unless you adjust assignment calendars.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the articles before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP

quixote wrote:
I am getting frustrated with how Project calculates(or doesn't)...I
know this is probably user error.
I have added tasks, indented some lines so they would be subtasks,
assigned a resource and added work hours. The subtask work hours are
not adding up to the main task..the task just has zero even though
subtasks have values and duration hasn't changed from the default.
Another issue...I have the start date from the past but some of the
subtasks have the current date and I can't change it...what am I
doing wrong??!!!

also...I played around with trying to set up a 24/7 calendar but it
didn't seem to work. I have an iterative project that should have
lots of predecessors that will just continue on regardless of the
time of day or what day it is...but I can't make sense of how
duration is being calculated...any ideas on this would be appreciated
too


Thanks


.



Relevant Pages

  • Re: How to set the week to 6 days and not 5
    ... Calendar, a "week" will still be 5 days so that is normal. ... Jan De Messemaeker ... Microsoft Project Most Valuable Professional ... - I create the three subtasks, assign each 1 week, ...
    (microsoft.public.project)
  • Re: Duration calculation
    ... To clarify -- changing the information under Tools> Options, Schedule ... For details on changing the working time in Project 2007, ... Modify the calendar through Tools> Change Working Time. ... View tab: Date format showing date and time. ...
    (microsoft.public.project)
  • Re: Holidays falling at weekends
    ... Welcome to this Microsoft Project newsgroup:) ... Once you've set up the Standard calendar, Project will not schedule work over those times - that's the purpose of setting up the calendars. ... FAQs, companion products and other useful Project information can be seen at this web address: http://project.mvps.org/faqs.htm ...
    (microsoft.public.project)
  • Re: Scheduling one event to occur first thing in the morning next day
    ... Jan De Messemaeker, Microsoft Project Most Valuable Professional ... Create a base calendar with working time 1 minute during the night ... Joe's last task is to load the sign onto a trailer, ...
    (microsoft.public.project)
  • Re: Real Life Practical Scheduling Constraint
    ... There is a workaround which involves a custom calendar, ... task set as the predecessor to the task you want to schedule. ... Insert a task before the task you wish to schedule and set the duration ... of delivering Microsoft Project training and on reflection I think it ...
    (microsoft.public.project)