Re: Highlighting overdue tasks



Very nice... is there any trick to see the impacted line items that are not
visible on the screen? My project is over 700 lines long. I like the
feature but now fear I may miss something unless I scan the whole document
for highlighted fields.

Headed in the right direction anyway, I like! :)
--
Michael Gwin
Program Manager
UnitedHealth Group


"JulieS" wrote:

Hello Michael,

Ensure that "Show Change Highlighting" in the View menu is enabled.

You may also be interested in Highlight filters to answer your point
under "Gold standard." See Project > Filtered For > More Filters,
select your custom filter and choose "Highlight". You can also
modify a View (View > More Views, Edit) to have all filters work as
highlight filters.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project

"Michael Gwin" <MichaelGwin@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message news:97F4E29C-3F79-4883-ACFF-03416F0ACCE7@xxxxxxxxxxxxxxxx
I have Project 2007 and I have not seen it change the cell
background color.
Is this an option I have to enable, or be in a specific view? Im
intrigued.
:)
--
Michael Gwin
Program Manager
UnitedHealth Group


"Jim Aksel" wrote:

Project 2007 meets the platinum standard. When you make a change
to a task,
all changed dates (rippled dates) change the cell background
color. There is
also a task driver pane that shows what condition is driving the
start date
of the selected task.

In all versions of project, if you set a status date
(Project/Project
Information...) and insert the Status (or Status Indicator)
column, it will
provide information concerning the current %Complete compared to
what it
should be for the task to be on schedule. That is, if the real
%complete is
15%, and 16% or more of the task duration has elapsed, the status
will show
late. Ahead of schedule tasks show on schedule, future tasks
show "future"
and completed tasks show "complete."

Your silver standard implies you are keying deadlines for tasks.
You really
do want to know those tasks are being driven to complete late. I
would leave
it alone.

Also, if a task has a finish date in the past you absolutely need
to extend
the duration if it is not complete. If you did not finish it
"yesterday"
then you need to tell Project when you expect it will be complete
so it will
drive the remaining tasks.

Finally, you can code some VBA to whatever rules you like and
then set a
flag or number field. Either of these can be set to display a
graphical
indicator.

Here are some tests we use:
1. Start date in the past with 0% Complete, needs new start date
after the
status date.
2. Finish date in the past with less than 100%, extend duration
to at least
the day after the status date unless rule 1 applies.
3. Start date to the right of the status date with %Complete not
0. You did
not start the work "tomorrw" it started "yesterday" and you need
to tell the
schedule that. You may finish it early, or, extend the duration
so the
finish date remains the same.
4. Task is 100% complete with a Finsih date to the right of the
status date.
Sorry, you did not finish the task "tomorrow", provide a real
date so a
successor activity can claim an early start.
5. Tasks with negative total slack. These tasks tell you the
schedule is
not viable as currently linked. Tinkering required.
6. Tasks where the immediate predecessor is not 100% and the task
is
claiming any %complete at all. This is somewhat minor because it
really just
means the predecessor task has not been broken down to sufficeint
detail.

All of these are easy to code (except #6). We use a flag field
and show a
red dot if any one or more tests fail. You could also use a
number field to
return the number of the failed test and color an icon
accordingly.

Your least expensive solution is an upgrade to P2007 as it will
take you
about a day to properly code and test the VBA mentioned.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Michael Gwin" wrote:

Ive read a few posts on this topic and what I really want
doesnt seem
possible but I thought Id ask specifically just in case.

I have a filter that will show me tasks due on a particular
day. What I
dont like is it shows me those tasks, and if they arent
complete, my first
instinct is to push them out. What I cant see are the
surrounding tasks to
see what impact Im making by pushing that date out.

So...

Platinum Standard: I wish MS Project would throw up flags when
you move a
date out on a task that has successors showing the ripple
effect in your
plan. I dont think Project does this... should be added.

Gold Standard: Use a filter or some indicator that would flag
certain tasks
while still showing the surrounding tasks (like red text or
something would
be nice) Id prefer this to be based on my filter criteria

Silver Standard: I know the indicator column will flag red
those tasks it
thinks are overdue. But it flags tasks that havent started yet
but are due
in the future as overdue as well. Can I change the rules of
the indicator to
truly show those tasks with a finish date in the past?

Thanks always, Id go out of my mind without this forum for
help! :)

Mike



.



Relevant Pages

  • RE: Highlighting overdue tasks
    ... I have Project 2007 and I have not seen it change the cell background color. ... and insert the Status (or Status Indicator) column, ... Ahead of schedule tasks show on schedule, ... flag or number field. ...
    (microsoft.public.project)
  • RE: Highlighting overdue tasks
    ... experience with VBA scripting but do catch on fast. ... and insert the Status (or Status Indicator) column, ... Ahead of schedule tasks show on schedule, ... flag or number field. ...
    (microsoft.public.project)
  • Re: Highlighting overdue tasks
    ... experience with VBA scripting but do catch on fast. ... and insert the Status (or Status Indicator) ... Ahead of schedule tasks show on schedule, ... flag or number field. ...
    (microsoft.public.project)
  • Re: Highlighting overdue tasks
    ... Like I set a view to use a filter I created for Overdue tasks. ... You may also be interested in Highlight filters to answer your point ... Ahead of schedule tasks show on schedule, ... flag or number field. ...
    (microsoft.public.project)
  • Re: Highlighting overdue tasks
    ... Then retry your filter. ... You may also be interested in Highlight filters to answer your point ... Ahead of schedule tasks show on schedule, ... flag or number field. ...
    (microsoft.public.project)

Quantcast