Hi,
No misunderstandings: my yes does NOT mean it is a crazy idea :-))
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
"Markarina" <markbs2@xxxxxxxxxxxxxx> wrote in message
news:c56c2fbf-b93e-4707-ae87-1aedb7a858a3@xxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx
I have a number of tasks and a number of resources, some of the
resources and need to work on specific tasks, but other than that I do
not have any dependencies, but I do have some that are higher priority
than others. I have some dates that need to be met.
I am wondering if I can actually use project to do all the scheduling
for me by just setting relative priorities and deadlined as required.
I think that this should work because my understanding of levelling is
such that tasks with a higher priority will be scheduled ahead of
tasks with a lower priority and that as long as I set all the tasks to
fixed work project should sort it out?
.
- References:
- Is this a crazy idea
- From: Markarina
- Is this a crazy idea
- Prev by Date: Re: Is this a crazy idea
- Next by Date: Re: Server 2007 Usage Statistics
- Previous by thread: Re: Is this a crazy idea
- Next by thread: Re: Is this a crazy idea
- Index(es):
Relevant Pages
|