Yes, the baseline shows where the task had been, but what were shooting for
here is showing the amount that was extended. We need the ability to show how
far the task was extended. The baseline shows how far a task was delayed, but
you don't know the amount of time it was extended.

"Jack Dahlgren MVP" wrote:

From tools menu, tracking sub-menu, select save baseline.
From the views menu, select the tracking gantt.

This will show your original plan as the baseline and the current plan as
separate bars.

-Jack Dahlgren

"c_robertson" <crobertson@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:DCEEA8BA-0232-44D5-A6B4-856DC2D73283@xxxxxxxxxxxxxxxx
I would like the ability to show a task's previous dates. Would this be
possible to display it as a faded taskbar? I know this is an exponential
ripple effect, but at least 1 step. This way when a project is delayed we
can
displayed the previous schedule overlayed by the current schedule.
Maybe just the ability to overlay a complete schedule, but faded. All the
schedulers I know try to devise a way to do this.

----------------
This post is a suggestion for Microsoft, and Microsoft responds to the
suggestions with the most votes. To vote for this suggestion, click the "I
Agree" button in the message pane. If you do not see the button, follow
this
link to open the suggestion in the Microsoft Web-based Newsreader and then
click "I Agree" in the message pane.

http://www.microsoft.com/office/community/en-us/default.mspx?mid=dceea8ba-0232-44d5-a6b4-856dc2d73283&dg=microsoft.public.project

.



Relevant Pages

  • Re: Automatic calculation w/ add duration to "planned start/finish
    ... What you are calling the "planned dates" - those dates that were the original schedule before we had to revise it after starting work - is what Project calls the "Baseline Dates." ... Using your terminology you could say the schedule doesn't show the plan, if that makes any sense, If we initially planned A to start 03 Apr and take 5 days so B would start 10 Apr, those are initially both the Scheduled Start and the Baseline Start. ... enter the tasks that have been done using the actual durations you obtained, and tasks still to come with their expected duration. ...
    (microsoft.public.project)
  • Re: Start versus Actual Start...
    ... Some other table options may show you Baseline Start, ... So Project is now displaying a schedule that it has calculated - it has ... > let's say due to a bad link assumption), Jones reports putting in 2 hours ... >>> estimated, resources assigned at 100%, resources leveled ...
    (microsoft.public.project)
  • Re: Project 2007 - Help is required
    ... The original scheduled dates will only be stored if you save a baseline ... You could input this data in Tracking Gantt view ... There is another table Variance which could be opened alongwith ... schedule is a schedule. ...
    (microsoft.public.project)
  • Re: Automatic calculation w/ add duration to "planned start/finish
    ... dates" - those dates that were the original schedule before we had to revise ... it after starting work - is what Project calls the "Baseline Dates." ... and tasks still to come with their expected duration. ... the actuals into the Actual Start, Finish, and Duration fields (display ...
    (microsoft.public.project)
  • Re: Showing % complete on baselines
    ... In my custom fields which generate the % complete on baseline gantt I use ... My "current plan" does not show work achieved ahead of the status date ... Its the baseline reflecting the other information I wished to ... > and so it really doesn't tell you if you're on schedule or not. ...
    (microsoft.public.project)