RE: Extra info for a Split task

Tech-Archive recommends: Speed Up your PC by fixing your registry



Jim,

I am confused; my understanding of the Stop and Resume fields is that they
are progress driven. Once the task is completed wouldn't the Stop and Resume
dates be the same as the task’s finish date and not the points where the
split occurs?

Darrell


"Jim Aksel" wrote:

Use the [Stop] and [Resume] fields.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"M_Arizaga" wrote:

I'm exporting a project plan to MS Excel and I want to view the dates for a
task that have been split.
I can export the Start an Finish fields but I need to export the date when
the task is suspended as well as the date when it's resumed.

I've tried in Project Pro 2003 and 2007 with no luck
.



Relevant Pages

  • RE: Extra info for a Split task
    ... field and when i put it back to 0%, the task is no longer split. ... Jim Aksel, MVP ... Check out my blog for more information: ... I've tried in Project Pro 2003 and 2007 with no luck ...
    (microsoft.public.project)
  • RE: Earned Value Visual Report
    ... Jim Aksel, MVP ... Check out my blog for more information: ... the cumulative totals all work out as well. ...
    (microsoft.public.project)
  • Re: I want to assign hours to my tasks and track that way. How?
    ... Jim Aksel, MVP ... Check out my blog for more information: ... Presumably by 'calendar' you mean the time-phased portion of the display ...
    (microsoft.public.project)
  • RE: Cost Calcs
    ... I'm checking out your blog, ... earned values terms this is called BCWS (Budgeted Cost of Work Scheduled). ... Actual Work and Remaining Duration. ... Jim Aksel, MVP ...
    (microsoft.public.project)
  • Re: Pert Analysis
    ... it does not add to the other add-in. ... On the blog, select Project Tips ... Jim Aksel, MVP ... I cannot make the Pert Analysis work on my computer. ...
    (microsoft.public.project)