Re: Change Hours in a Work Week

Tech-Archive recommends: Repair Windows Errors & Optimize Windows Performance



What are these variations in hours based upon? If they are essentially random in nature, there can be no way of programming them to some arbitrary point in the future.

Depending on how they are derived, there might be some scope for VBA.

Steve wrote:
Thanks for the reply. Unfortunately - it doesn't answer my question. I can change working hours. The issue is the change affects the entire calendar. I need to change specific weeks for specific resources for specific hours.

If you can advise on that - it would be greatly appreciated.

Thanks.

"Jim Aksel" wrote:

You can imply an answer from my post earlier today titled: "HELP with Task Duration/Calendar." I posted to Grace

In there I explain how to make certain days (weeks) work days. You will need to change the work hours.
--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com



"Steve" wrote:

How do I change the numbers of hours in a work week for the specific week?
Ex - Week 1: 5x8 = 40 hrs
Week 2: 5x12 = 60 hrs
Week 3: 5x10 = 50 hrs.
Whatever the last entry is becomes the default for the entire calendar for the resource. I need specific weeks to refelct specific total hours.

Thanks

Steve
.



Relevant Pages

  • Re: Change Hours in a Work Week
    ... Steve wrote: ... I need to change specific weeks for specific resources for specific hours. ... Jim Aksel, MVP ... Whatever the last entry is becomes the default for the entire calendar for the resource. ...
    (microsoft.public.project)
  • Re: Change Hours in a Work Week
    ... alter the working time for each week, ... If you are referring to the setting in Tools> Options, Calendar -- ... Jim Aksel, MVP ... "Steve" wrote: ...
    (microsoft.public.project)
  • RE: Change Hours in a Work Week
    ... The issue is the change affects the entire calendar. ... need to change specific weeks for specific resources for specific hours. ... Jim Aksel, MVP ... "Steve" wrote: ...
    (microsoft.public.project)
  • RE: What am I doing wrong tracking progress?
    ... I assign resources to tasks. ... the automatic leveling to split tasks, and add the urgent task to the ... assume that there is some overhead, e.g., a task that is estimated to ... calendar to block off some hours in each day for overhead. ...
    (microsoft.public.project)
  • Re: Printing the calendar view
    ... For your request, #16 for writing simple macros, #22 for filters and #24 ... 2- filter by "using resources within date range" and printing). ... Also, I don't know anything much about macros, but is there a way to set ... > filtered calendar view? ...
    (microsoft.public.project)