Re: Fully Allocate a Resource
- From: Dave <nobody@xxxxxxxxxxxxx>
- Date: Sat, 11 Oct 2008 08:06:06 +0100
You can make project display the start time by going to tools, options and selecting the view tab. In the date format you can opt to show or hide the time.
As a general observation, do you actually have to track what your resources are doing minute by minute? That's a very fine level of granularity. If you are only interested in ensuring that they get a number of activities done in a day then I would suggest day-by-day levelling or even week-by-week levelling might be more appropriate although your particular circumstances may dictate otherwise.
I don't understand how what you have done has resolved the problem and wonder whether you are expecting too much from the levelling engine.
Levelling is not an optimisation tool in that it won't adjust the work to fill the gaps in a resource's working day. It actually does something closer to the opposite - it simply delays tasks until there are no overallocations in the resource's schedule.
If, after levelling, a resource is not working sufficiently many hours in a day then you need to manually adjust the length of that task (and possibly level again - you may find it useful to fix those elements of the plan you are happy with by setting their priority to 1000).
You shouldn't have to adjust the contour and I wouldn't worry about it. By definition, unless the resource works exactly the same number of hours every day on a task then it is contoured. Instead, if I wasn't happy with the hours that a resource had been scheduled to work then I would alter that either by directly entering the planned hours or by adjusting the length of the task, although when doing this you need to consider the totality of hours worked by the resource across all the tasks occurring on that day.
Vic wrote:
Hi Julie,.
On the leveling I didn't allow splitting of a task. And I'm not sure how to check the time of a task starting. Please let me know on that just out of curiousity. But I don't believe that is it because it's many days and many tasks that it happens.
I was able to resolve the problem by changing the Work Contour and prioritizing some tasks. When I entered Actual Work it changed the Work Contour from "Flat" to "Contour" - is that normal? So I changed them back to Flat and in addition to the prioritization that seemed to start scheduling the work so they had an 8 hour day (or at least close to it in some cases).
Hope that makes sense. While it seems to be corrected, I would still be curious to know why it does that and if there's a better way to handle the situation. Your help is appreciated.
- Follow-Ups:
- Re: Fully Allocate a Resource
- From: Vic
- Re: Fully Allocate a Resource
- References:
- Fully Allocate a Resource
- From: Vic
- Re: Fully Allocate a Resource
- From: Gérard Ducouret
- Re: Fully Allocate a Resource
- From: Vic
- Re: Fully Allocate a Resource
- From: Gérard Ducouret
- Re: Fully Allocate a Resource
- From: Vic
- Re: Fully Allocate a Resource
- From: JulieS
- Re: Fully Allocate a Resource
- From: Vic
- Fully Allocate a Resource
- Prev by Date: Re: Changes not saved when altering dependency type
- Next by Date: Re: MS Project Default View..getting Distracted
- Previous by thread: Re: Fully Allocate a Resource
- Next by thread: Re: Fully Allocate a Resource
- Index(es):
Relevant Pages
|