Re: Fully Allocate a Resource

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



Hi Vic,

Pardon me for bumping in, but what time in the day does the task
begin? If the task doesn't begin at the start of the working day, I
wouldn't expect to get 8 hours of work in.

Also, you mention that you are using Resource Leveling on a minute
by minute basis. It's possible that in order to resolve
overallocation that the task has been split to allow other tasks to
be scheduled on that day.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project


"Vic" <Vic@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:F669607B-58BA-40D1-989D-838DB22B93E6@xxxxxxxxxxxxxxxx
Thanks.

Sorry, that's what I've been using, the Actual Work. On occasion
I might
have entered something in the Work field to force a task to start
earlier
(same resource working on two tasks but Project placed them in a
different
sequence than I wanted).

Do you think this is caused if I entered something in Work field?
Is there
a way to correct that?


--
Vic


"Gérard Ducouret" wrote:

Vic,

If you want to enter work values based on how much they've worked
on a task,
don't use the "Work" field but the "Actual Work" field.
Hope this helps,

Gérard Ducouret


"Vic" <Vic@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message de
news:
63533834-B45E-4B9D-8EBD-826FBF115C15@xxxxxxxxxxxxxxxx
Yes, I've been entering work values based on how much they've
worked on a
task. That seems to be the tasks this happens with. So you're
definitely
on
to something :). Thanks.

What should I be doing different or how can I adjust so it
schedules the
remaining hours appropriately (ie. 8 hours per day)?


--
Vic


"Gérard Ducouret" wrote:

Vic,

Are you sure that somebody did not enter a Work value for
these tasks?
For example 20h of Work on a task, the Duration of which is
10d.
If you click Assign for a resource, Project calculate Units =
0.25 and
the
work for each day is 2h.

Gérard Ducouret

"Vic" <Vic@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message
de news:
E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@xxxxxxxxxxxxxxxx
Hi,

I'm working in Project 2003 and I'm having an issue where it
won't
fully
allocate a resource who is assigned to a task at 100%. This
is
happening
in
several instances where it only assigns someone for say 2
hrs per day
(instead of 8). Again they are 100% on the task and I can't
find a
valid
reason for this. I am using leveling as well on a Minute by
Minute
basis.

Any ideas?

--
Vic








.



Relevant Pages

  • RE: OT RAG formula
    ... I have some good news and some bad news. ... The formula does respect working ... more than one resource assigned. ... /number of days between current date and baseline finish ...
    (microsoft.public.project)
  • Re: Accidently deleted "news" from Go menu. Can I restore it?
    ... I needed that fix! ... It's so nice to have a resource available by ... > Internet Options and change the default newsreader to Outlook Express. ... >>I try to put News to Go menu and accidently delete it. ...
    (microsoft.public.outlook.installation)
  • Re: Concise Resource Reporting
    ... message de news: uuLGykUgJHA.5540@xxxxxxxxxxxxxxxxxxxxxxx ... Try going to the Resource Usage view. ... Resource 1 and 2 (hrs) ... Group assignments, ...
    (microsoft.public.project)
  • Child Diabetes
    ... Hi I am a new member of this group and I also want to share my ... about increase child diabetes status ever day in my blog. ... You will also love some other world information, news, Real life ...
    (misc.health.diabetes)
  • Re: New Tasks added to plan start in the past (resource leveling)
    ... Are you posting the hours that your resources have put on the tasks into the ... Work field or into the Actual Work field? ... of a resource scheduled to work 8 hours in a day but leaving 2 hours early. ... Leveling will not push any>> task into the past. ...
    (microsoft.public.project)