Re: Fully Allocate a Resource
- From: Vic <Vic@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Wed, 8 Oct 2008 13:23:04 -0700
Yes, I've been entering work values based on how much they've worked on a
task. That seems to be the tasks this happens with. So you're definitely on
to something :). Thanks.
What should I be doing different or how can I adjust so it schedules the
remaining hours appropriately (ie. 8 hours per day)?
--
Vic
"Gérard Ducouret" wrote:
Vic,.
Are you sure that somebody did not enter a Work value for these tasks?
For example 20h of Work on a task, the Duration of which is 10d.
If you click Assign for a resource, Project calculate Units = 0.25 and the
work for each day is 2h.
Gérard Ducouret
"Vic" <Vic@xxxxxxxxxxxxxxxxxxxxxxxxx> a écrit dans le message de news:
E8976C5B-DE58-4D13-BEDE-9408C24BA8E1@xxxxxxxxxxxxxxxx
Hi,
I'm working in Project 2003 and I'm having an issue where it won't fully
allocate a resource who is assigned to a task at 100%. This is happening
in
several instances where it only assigns someone for say 2 hrs per day
(instead of 8). Again they are 100% on the task and I can't find a valid
reason for this. I am using leveling as well on a Minute by Minute basis.
Any ideas?
--
Vic
- Follow-Ups:
- Re: Fully Allocate a Resource
- From: Gérard Ducouret
- Re: Fully Allocate a Resource
- References:
- Fully Allocate a Resource
- From: Vic
- Re: Fully Allocate a Resource
- From: Gérard Ducouret
- Fully Allocate a Resource
- Prev by Date: Re: Remove "days" from duration field(s)
- Next by Date: Re: Fully Allocate a Resource
- Previous by thread: Re: Fully Allocate a Resource
- Next by thread: Re: Fully Allocate a Resource
- Index(es):
Relevant Pages
|