HI, I had removed the 'fiscal' setting. Recalculating the project seemed to
work, thanks!

"Jack Dahlgren MVP" wrote:

Your timescale is probably set to display "fiscal" dates.
Double click the timescale on the chart and check the options.
If that doesn't seem to be the problem, hit the F9 key and see what happens
when the project recalculates.

-Jack Dahlgren

"mmckeen" <mmckeen@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:CBB281D2-7BAF-41B0-B9A7-35F5E4CBF033@xxxxxxxxxxxxxxxx
Hi, hoping someone can help. I've noticed that some of the summary tasks
are
the wrong length and for the wrong durations to the tasks that they
summarize. For example, I have 3 tasks with the earliest start date of
10/1
and the latest finish is 10/16. The summary task is 10/21 to 11/10,
totally
outside of the range. This is appearing in multiple instances, and then
there are some summary tasks that are behaving as expected. Any ideas?
Thanks in advance.

.



Relevant Pages

  • Re: My subtasks have no cost, but summary task does?
    ... "Jack Dahlgren MVP" wrote: ... There was a bug in older versions of project which summary tasks retained ... Note that you can not delete a summary task without affecting the subtasks, ... the summary tasks I have a cost, but the subtasks don't have any cost, and ...
    (microsoft.public.project)
  • Re: My subtasks have no cost, but summary task does?
    ... "Jack Dahlgren MVP" wrote: ... There was a bug in older versions of project which summary tasks retained ... costs of deleted subtasks. ... the summary tasks I have a cost, but the subtasks don't have any cost, ...
    (microsoft.public.project)