Re: Length/duration of my summary bars wrong in Proj 2007
- From: mmckeen <mmckeen@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Fri, 3 Oct 2008 08:53:00 -0700
HI, I had removed the 'fiscal' setting. Recalculating the project seemed to
work, thanks!
"Jack Dahlgren MVP" wrote:
Your timescale is probably set to display "fiscal" dates..
Double click the timescale on the chart and check the options.
If that doesn't seem to be the problem, hit the F9 key and see what happens
when the project recalculates.
-Jack Dahlgren
"mmckeen" <mmckeen@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:CBB281D2-7BAF-41B0-B9A7-35F5E4CBF033@xxxxxxxxxxxxxxxx
Hi, hoping someone can help. I've noticed that some of the summary tasks
are
the wrong length and for the wrong durations to the tasks that they
summarize. For example, I have 3 tasks with the earliest start date of
10/1
and the latest finish is 10/16. The summary task is 10/21 to 11/10,
totally
outside of the range. This is appearing in multiple instances, and then
there are some summary tasks that are behaving as expected. Any ideas?
Thanks in advance.
- References:
- Length/duration of my summary bars wrong in Proj 2007
- From: mmckeen
- Length/duration of my summary bars wrong in Proj 2007
- Prev by Date: Re: How to print time range on Gantt chart
- Next by Date: printing pdf to view on cpu
- Previous by thread: Length/duration of my summary bars wrong in Proj 2007
- Next by thread: printing pdf to view on cpu
- Index(es):
Relevant Pages
|