Length/duration of my summary bars wrong in Proj 2007



Hi, hoping someone can help. I've noticed that some of the summary tasks are
the wrong length and for the wrong durations to the tasks that they
summarize. For example, I have 3 tasks with the earliest start date of 10/1
and the latest finish is 10/16. The summary task is 10/21 to 11/10, totally
outside of the range. This is appearing in multiple instances, and then
there are some summary tasks that are behaving as expected. Any ideas?
Thanks in advance.
.



Relevant Pages

  • Re: how to calculate the sum of durations of subtasks for a summar
    ... summary tasks and other tasks. ... > Thanks Rod. ... >> Visit www.msproject-systems.com for Project Companion Tools and more ... >>> of subtasks's durations, not the longest duration for their ...
    (microsoft.public.project.vba)
  • Re: CHANGING DATES & DURATION IN A HEADING
    ... The durations of Summary tasks, e.g. the start/end dates will ... > formed groups with headings using the indent arrow. ...
    (microsoft.public.project)
  • Re: Fractional Durations in Summary Tasks
    ... For availability check: ... fractional totals showing up in the summary tasks even though I have been ... I would expect thhe durations to be either ...
    (microsoft.public.project)
  • durations problem?
    ... i have problem with durations ... but while i change them the summary tasks are ... in week & subtasks in day & when i change them to week ...
    (microsoft.public.project.standard_and_server)
  • Re: Project Summary Task Durations
    ... Rollup of durations is calculating the difference between first start and ... Summary tasks followed by subtasks. ... calculating my summary task durations. ...
    (microsoft.public.project)