Re: Deleting Inserted Projects
- From: "Rod Gill" <rodATproject-systemsDOTcoDOTnz>
- Date: Wed, 1 Oct 2008 09:45:19 +1300
If you double-click the header, can you deselect the Link to project option under the Advanced tab? If so click OK. Now all data will be copied into the master and you can delete it safely.
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"Richard W" <Richard W@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message news:414E254A-50B0-4D6C-864B-8D7B80CF1180@xxxxxxxxxxxxxxxx
I have a master project (in MSP 2003) within which I have inserted a number
of sub projects to form a consolidated project. However I am now unable to
delete any of the subprojects from the master project. It will delete the
activities within the sub project, but not its "header" that appears as an
activity in the master project. I am not using resource pools on any of the
projects. In my business we have just converted to 2003 from 2000 and was
unsure whether it is a system configuration problem.
Any ideas?
.
- Follow-Ups:
- Re: Deleting Inserted Projects
- From: Richard W
- Re: Deleting Inserted Projects
- References:
- Deleting Inserted Projects
- From: Richard W
- Deleting Inserted Projects
- Prev by Date: Re: Asign many tasks to the same resource
- Next by Date: Re: Cell Formatting - Text and Detail Cells
- Previous by thread: Deleting Inserted Projects
- Next by thread: Re: Deleting Inserted Projects
- Index(es):
Relevant Pages
|