Re: What is the Most Accepted Method to Status a Schedule?

Tech-Archive recommends: Speed Up your PC by fixing your registry



On Wed, 25 Jun 2008 08:57:47 -0700 (PDT), JJ wrote:

In my 10 years of scheduling, I have come across several ways of
getting status for a schedule. Usually, I just go with whatever the
"norm" is in the company that I am working for. I have seen the
following methods for getting status:
1) Request dates (actual or forecast) and % Complete
2) Request Remaining Work and Finish Dates
3) Request Remaining Duration (regardless of Finish Dates)
4) Request Finish Dates and alter Remaining Duration to hit Finish
Date

The IMSs are usually resource loaded, used for Earned Value, status is
taken weekly, and Actual Costs are NOT captured in the IMS. In #'s
2-4, the "% Complete" Value is statused to time now, which is usually
the Friday of the previous week.

So... is there an preferred or more accepted method of getting status
for an IMS?

Thanks!
JJ

Not sure what an "IMS" is, but I'm guessing something like "Internal
Measure of Success". Based on my experience (over 30 yrs), I favor 3 or 4
or some combination thereof. I've found that resources find it easier to
fudge % Complete than remaining work or duration, so I prefer that %
Complete be calculated based on Actual Work and Remaining Work. (I'm really
referring to % Work Complete here, not Project's virtually useless %
Duration Complete)
If there's a large discrepancy between Remaining Work and Remaining
Duration, as there often is in some kinds of work, then both should be
tracked and the schedule updated accordingly.
I don't know why Actual Costs are not captured, other than sometimes, in
some systems, it's difficult to capture them. Obviously they're needed for
EVA.
Hope this helps in your world.
.



Relevant Pages

  • What is the Most Accepted Method to Status a Schedule?
    ... In my 10 years of scheduling, I have come across several ways of ... Request dates and % Complete ... Request Finish Dates and alter Remaining Duration to hit Finish ... and Actual Costs are NOT captured in the IMS. ...
    (microsoft.public.project)
  • Remaining Duration and % Complete
    ... I want to include % Complete and Remaining Duration when request a ... status update from people responsible for tasks on a schedule. ... such that I fulfill both requirements. ... Task A Duration: 20-day task ...
    (microsoft.public.project)
  • Re: Automatic calculation w/ add duration to "planned start/finish
    ... dates" - those dates that were the original schedule before we had to revise ... it after starting work - is what Project calls the "Baseline Dates." ... and tasks still to come with their expected duration. ... the actuals into the Actual Start, Finish, and Duration fields (display ...
    (microsoft.public.project)
  • Re: Formula Questions
    ... Start date and then that value is divided by task duration. ... we have many schedules with only one resource ... We baselline that and use SPI as described ... becomes important as it gives you ahead or behind schedule. ...
    (microsoft.public.project)
  • Re: Automatic calculation w/ add duration to "planned start/finish
    ... What you are calling the "planned dates" - those dates that were the original schedule before we had to revise it after starting work - is what Project calls the "Baseline Dates." ... Using your terminology you could say the schedule doesn't show the plan, if that makes any sense, If we initially planned A to start 03 Apr and take 5 days so B would start 10 Apr, those are initially both the Scheduled Start and the Baseline Start. ... enter the tasks that have been done using the actual durations you obtained, and tasks still to come with their expected duration. ...
    (microsoft.public.project)