RE: multi WBS plans
- From: sedrazi <amateurman@xxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 19 Jun 2008 14:08:01 -0700
"lucky" wrote:
Yes, Resource management in my project is using ERP too. If I weredear Luky
you I will use tool > Customize field and using formula by flag
and number field incase department level and location is changing
with out loosing calulate of entire project.
sorry for being late, I was investigating for what you said but I couldn't
do it (thanks for care). Besides I didn't know how to explain my plan in this
little plain
text box. but I'll try anyway, assume:
you have a plan with 2 main levels of tasks and below these you have
hundreds(or thousands) of low level tasks. such as:
Dep. Spec. Tasks
level level level
------- ------- -------
PROJECT X_____________________
*Design
.electric
-Task01
-Task02
- ...
.mechanic
-Task11
-Task12
- ...
*Constr.
.electric
-Task21
-Task22
- ...
.mechanic
-Task31
-Task32
- ...
And now you want to chang levels(2 main levels) to have a new look and
calculations for these levels, eg:
Dep. Spec. Tasks
level level level
------- ------- -------
PROJECT X_____________________
*electric
.Design
-Task01
-Task02
- ...
.Constr.
-Task21
-Task22
- ...
*mechanic
.Design
-Task11
-Task12
- ...
.Constr.
-Task31
-Task32
- ...
In this case, tasks in main levels are not the same as above but with this
method you can answer all other departments needs (accounting, storage, etc).
at the end I must thank microsoft (& ofcorse you) & ask for quick response
from microsoft.
.
- Follow-Ups:
- RE: multi WBS plans
- From: lucky
- RE: multi WBS plans
- References:
- multi WBS plans
- From: sedrazi
- multi WBS plans
- Prev by Date: Re: Managing large programs with many streams
- Next by Date: Re: conversion issues from 2007 to 2003
- Previous by thread: multi WBS plans
- Next by thread: RE: multi WBS plans
- Index(es):