Re: Physical Percent Complete

Tech Tip: Click here to run a free scan for Windows Errors and optimize PC performance



You're welcome Andrew. Glad to have helped and thanks for the
feedback.

Julie

"andrew-k" <andrewk@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:75CA1C20-0100-4ED7-8316-D0C32A90071E@xxxxxxxxxxxxxxxx
Julie,
Thank you especially for 3) below. I had assumed that setting
Physical %
Complete as the default EV method in Tools, Options was all I had to
do.
--
Best,
Andrew-K


"JulieS" wrote:

"bvolkertcc" <bvolkertcc@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message
news:77E6CF04-021D-44F8-A1DA-B89B3B11F21D@xxxxxxxxxxxxxxxx
How do I enable the physical percent complete to roll up on the
summary task?

Thank you!

Hello,

In order for Physical % Complete to roll up to a summary task, the
following must be true:
1) Resources need to be assigned to the tasks.
2) Resources need to have costs associated (even $1 per hour in the
standard rate field will do).
3) The earned value method for *all* tasks must be set to Physical
%
complete. Insert the earned value method field in the task ***
and
ensure all tasks are set correctly.
4) A baseline needs to be saved after steps 1-3 have been
completed.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project








.


Quantcast