Re: gantt bar start

Tech-Archive recommends: Speed Up your PC by fixing your registry



Hello Toltec,

What time does the task start? It is usual for project to schedule
tasks to begin at the start date and time of the project but it sounds
as though the start time of the project is off.

Switch to a date format that shows time through Tools > Options, View
tab. Then check the project start date through Project > Project
Information.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project

"Toltec" <Toltec@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:D0E6363C-C618-4821-B9D9-4C68AE34FD0B@xxxxxxxxxxxxxxxx
When I enter a new task, the gantt bar seems to start at the end of
the first
day. In other words, if the duration is just 1 day, there is no
bar. How do
I have it start at the begining of the first day? My timeline is
weeks/days.


.



Relevant Pages

  • Re: interesting article on quantum cryptography
    ... Get your most smoothing revelation concerning my schedule. ... Georgette, still ... begining, adds almost about, as the lane cheers off their retreat. ...
    (sci.crypt)
  • Re: Duration not working correctly
    ... the bar styles are formatted (Format/Bar Styles). ... Service Pack 2 (SP2) for Project 2003 was released to resolve several ... start date so it enters the schedule start date into the Actual Start ...
    (microsoft.public.project)
  • Re: Scheduling full and partial resources across tasks (flex time)
    ... though the task's bar extends over non-working days it hasn't scheduled work ... The task bar simply extends from the time work starts on the task ... the weekend even though it is non-working time. ... it tries to schedule me even on days I have marked as> non-working days!! ...
    (microsoft.public.project)
  • Re: Scheduled v. Actual Progess
    ... The Tracking Gantt View shows the bars you need, ... The Tracking Table shows the fields that you need to fill in the progress ... Have a look at the bar styles in the Tracking Gantt View to ... BTW - Or schedule is not resource loaded, it is simply a Gantt Chart. ...
    (microsoft.public.project)
  • Re: Scheduled v. Actual Progess
    ... The Tracking Gantt View shows the bars you need, ... The Tracking Table shows the fields that you need to fill in the progress ... Have a look at the bar styles in the Tracking Gantt View to ... BTW - Or schedule is not resource loaded, it is simply a Gantt Chart. ...
    (microsoft.public.project)