Re: BCWP and BCWS
- From: Anna <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx>
- Date: Thu, 8 May 2008 10:14:03 -0700
I did some reading of past comments and saw resources that were assigned need
a value in it even $1/hr would work. I tried that and it didn't work.
I'll wait and see what you come up with. In the mean time I will contnue to
try out your suggestion to see if that will fix the problem.
"JulieS" wrote:
Hi Anna,.
Sorry for the delay in replying. I haven't had a great deal of time
to experiment, but I believe the reason you are not seeing values is
because your resources do not have any costs associated with them.
You are using solely fixed costs and as such, your assignments do not
have costs associated.
If you view the Resource Usage view and show BCWS, BWCP, ACWP in the
timescaled portion (left side) you'll see zeros. I can't experiment
right now, but you may be able to get what you want by modifying one
of the task reports to add those fields.
I'll work on this later and see what I can come up with and post back
Julie
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:13A68367-0C50-41F8-8773-C550EF4DAD40@xxxxxxxxxxxxxxxx
Thanks to all of you, all Fields are adding up correctly! You have
no clue as
to how happy I am right now because I have been battling this for
weeks all
on my own. Talk about stubborn! I just have one small problem ....
Now that everything is adding up correctly, when I try to generate
an earned
value over time report by going to reports/visual
reports/excel/earned value
over time report/view, then clicking on Assignment Usage with EV
tab, I am
receiving 0 values. If I double click the Q2 it will drop down the
weeks. If
I double click the items listed under type in the Pivot table field
list, the
only value showing is under costs.
How do you get the values to read under the planned, earned and
actuals
columns.
P.S. I'm working in MS Project 2007 and the service pack is
installed.
"Anna" wrote:
Thanks! I will try it out and let everyone know.
"Rod Gill" wrote:
As Julie said % complete is not accurate. I would go further and
say that
earned value reporting when you only use % complete is not all
all accurate
and will likely be misleading. The only way to get accurate
earned value
reports is by accurate scheduling of resources and actual hours
per day
updating (usually via a time*** system).
--
Rod Gill
Microsoft MVP for Project
Author of the only book on Project VBA, see:
http://www.projectvbabook.com
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:E016E7EC-6013-40FC-BA77-CDA2D9833A2E@xxxxxxxxxxxxxxxx
Awesome! I will play around with this tomorrow and see how
everything
works
out. I really appreciate all your help and suggestions. I'll
let you know
how
it all worked out. Thanks again and take care.
"JulieS" wrote:
Hi Anna,
Yes. By using actual and remaining duration, Project
calculates %
complete.
Percent complete = actual duration/duration * 100
From help:
"If you type a value in the % Complete field, Project
automatically
calculates actual duration and remaining duration. Likewise,
entering
a value in the Actual Duration or Remaining Duration field
automatically recalculates the other fields."
Julie
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:2D122A23-7B16-4799-8CCF-2CB33386C710@xxxxxxxxxxxxxxxx
If I go with tracking actual against remaining durations, do
I still
keep the
Earned Value Method = % Complete in the field like Andrew
suggested?
Does
Project automatically calculate acutual and remaining
durations?
"JulieS" wrote:
Hi Anna,
Don't worry about asking questions, that's what the
newsgroup is
here
for :-)
No you shouldn't save a new baseline. You should be able
to run
the
report with the existing baseline.
Just a quick comment on % complete. Most of the regular
posters
here
do not recommend % complete as a method of tracking. I
suggest
tracking actual and remaining duration which will calculate
and
update
% complete. For most people it's more accurate than %
complete.
I hope this helps.
Julie
Project MVP
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:8CF46B0D-B0AC-4A24-AD55-DDFB39F87582@xxxxxxxxxxxxxxxx
I hope this is the last question. Each week I will go in
and track
the
progress by entering % complete, do I need to save the
baseline
to a
new
baseline every week and will this generate an Earned
Value Over
Time
Report
through visual reports?
"JulieS" wrote:
Hi Anna,
Yes, I do mean a standard rate. If you use fixed costs
as
Andrew
suggests it should also work. Assign the fixed costs,
save a
baseline
and it should populate BAC (baseline cost).
Julie
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in message
news:286298CE-246B-40A1-9024-68CF4F6DCFB3@xxxxxxxxxxxxxxxx
Hi Julie,
Yes, Resources were loaded. What do you mean by
standard
rates?
If
it's an
hourly rate that I need to include for a resource,
then it's
no
good
because
all that is provided to me is a lump sum cost from the
contractor
for that
task.
Thats why I assumed that I had to put the lump sum in
the BAC
field.
"JulieS" wrote:
Hello Anna,
Pardon me for bumping in. In order for Project to
calculate
BCWP
and
BCWS you need:
1) Resources with standard rates assigned to tasks to
create
work.
2) Saved a baseline.
3) Set a status date
4) Applied tracking information
As you don't say specifically that you've assigned
resources,
my
guess
is you haven't. Therefore no work scheduled,
therefore no
BCWP.
When
you save a baseline it will populate BAC for you - no
need to
enter
it
in manually.
See the help topic "Analyze project performance with
earned
value
analysis".
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit http://project.mvps.org/ for the FAQs and
additional
information
about Microsoft Project
"Anna" <Anna@xxxxxxxxxxxxxxxxxxxxxxxxx> wrote in
message
news:25727D9B-C3B1-408E-9F2E-09A8364E7386@xxxxxxxxxxxxxxxx
I have Service Pack 1 installed. I tried Steps 1 and
2 and
then
I
went to
tables/more tables/earned value to check and see if
the
BCWP
and
BCWS
calculated and it didn't. I know that I'm doing
something
wrong,
but
I don't
know what. Do I need to save another baseline in
order for
this
to
work?
Do you have any material that can walk me through
the step
by
step
process
of entering lump sum costs into a task and then
being able
to
generate an
Earned Value report by exporting to excel?
"Andrew Lavinsky" wrote:
Might be a couple of things:
1) Set the Status Date in Project > Project
Information
2) Make sure that the task Earned Value
calculation is set
to
%
Complete
(which is the default). I think that's Tools >
Options >
Calculations, but
on existing tasks, you have to expose the field,
which is
Earned
Value Method
3) If you're using Project 2007, make sure that
- Follow-Ups:
- Re: BCWP and BCWS
- From: JulieS
- Re: BCWP and BCWS
- References:
- BCWP and BCWS
- From: Anna
- RE: BCWP and BCWS
- From: Andrew Lavinsky
- RE: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: JulieS
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: JulieS
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: JulieS
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: JulieS
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: Rod Gill
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: Anna
- Re: BCWP and BCWS
- From: JulieS
- BCWP and BCWS
- Prev by Date: Re: MS Project Server 2003 AND 2007 on one machine
- Next by Date: Alternative View to a Schedule - Need Help!
- Previous by thread: Re: BCWP and BCWS
- Next by thread: Re: BCWP and BCWS
- Index(es):
Loading